Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
24/09/2018
|
eds
|
|
2
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
25/09/2018
|
Regarding objection
|
|
3
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
18/10/2018
|
Please do needful objections raised by Nodal officer
|
|
4
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
06/02/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
14/02/2019
|
Reply of EDS
|
|
6
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
14/02/2019
|
Reply by DFO
|
|
7
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
27/02/2019
|
eds
|
|
8
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
27/02/2019
|
Regarding objection
|
|
9
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
11/03/2019
|
Kindly do needful objections
|
|
10
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
27/03/2019
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
03/04/2019
|
reply of eds
|
|
12
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
03/04/2019
|
Reply by DFO
|
|
13
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
12/04/2019
|
KML file of Left side of CA Site needs to be uploaded. Hard Copy of Part II needs to be uploaded in Sr. No. 16. The polygon of forest area is being shown in polygon of non forest area of project site.
|
|
14
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
15/04/2019
|
KML file of Left side of CA Site needs to be uploaded. Hard Copy of Part II needs to be uploaded in Sr. No. 16. The polygon of forest area is being shown in polygon of non forest area of project site.
|
|
15
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
25/04/2019
|
Reply
|
|
16
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
25/04/2019
|
Reply by DFO
|
|
17
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
16/07/2019
|
eds
|
|
18
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
16/07/2019
|
Regarding objection
|
|
19
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
01/08/2019
|
Correct the KML File
|
|
20
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
01/08/2019
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
27/08/2019
|
reply of EDs
|
|
22
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
27/08/2019
|
Reply by DFO
|
|
23
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
11/09/2019
|
Upload CA Scheme of 100 plants. There is a gap between polygons of forest area and non forest area. So upload correct KML of Project Site.
|
|
24
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
13/09/2019
|
Upload CA Scheme of 100 plants. There is a gap between polygons of forest area and non forest area. So upload correct KML of Project Site.
|
|
25
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
04/10/2019
|
Please coorected KML of Proejct Site
|
|
26
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
04/10/2019
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
14/10/2019
|
Reply of EDS
|
|
28
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
15/10/2019
|
Reply by DFO
|
|
29
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
05/11/2019
|
Objections
|
|
30
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
05/11/2019
|
Regarding objection
|
|
31
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
27/11/2019
|
Reply of EDS
|
|
32
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
28/11/2019
|
Reply by DFO
|
|
33
|
State secretary
|
EDS
|
Nodal Officer
|
07/01/2020
|
EDS
|
|
34
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
07/01/2020
|
EDS
|
|
35
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
07/01/2020
|
Regarding objection
|
|
36
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
13/01/2020
|
reply of eds
|
|
37
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
13/01/2020
|
Reply by DFO
|
|
38
|
Nodal Officer
|
REPLY
|
State secretary
|
30/01/2020
|
Reply
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
19/05/2020
|
eds
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
02/07/2020
|
eds
|
|
41
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
10/07/2020
|
eds
|
|
42
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
10/07/2020
|
Regarding objection
|
|
43
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
27/08/2020
|
objection clear
|
|
44
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
28/08/2020
|
Reply by DFO
|
|
45
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
16/09/2020
|
Violation as mentioned by DFO in part-II to be inserted in Part-III to V of the
on-line proposal.
|
|
46
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
17/09/2020
|
Please add Certificate, Objection Clear Letter, Revise Violation Report , PWD NOC, Please revise CA Scheme and Land Suitability Certificate
|
|
47
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
17/09/2020
|
objection move
|
|
48
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
18/09/2020
|
Please correct date of PWD NOC 26.7.2017 in Letter, Part-2 and Site Inspection Report.
|
|
49
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
21/09/2020
|
OBJECTION MOVE
|
|
50
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
21/09/2020
|
Please correct CLU date 27.3.2018 in objection clear letter.
|
|
51
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
21/09/2020
|
objection move
|
|
52
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
21/09/2020
|
Please uploaded violation report
|
|
53
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
22/09/2020
|
OBJECTION MOVE
|
|
54
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
23/09/2020
|
Please add part-3 in Additional Documents
|
|
55
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
25/09/2020
|
MOVE
|
|
56
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
25/09/2020
|
Reply by DFO Part-3 added
|
|
57
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
21/10/2020
|
Reply letter is not uploaded
|
|
58
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
21/10/2020
|
Reply letter is not uploaded
|
|
59
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
24/10/2020
|
reply letter done
|
|
60
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
25/10/2020
|
Reply by DFO
|
|
61
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
23/11/2020
|
eds
|
|
62
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
23/11/2020
|
Regarding objection
|
|
63
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
19/12/2020
|
OBJECTION MOVE
|
|
64
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
19/12/2020
|
Reply by DFO
|
|
65
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
30/12/2020
|
Please make specific recommendations in Part III.
|
|
66
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
30/12/2020
|
Part 3 is attached on Sr No 2
|
|
67
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
09/03/2021
|
eds
|
|
68
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
10/03/2021
|
Regarding objection
|
|
69
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
03/05/2021
|
Please send non forest correct undertaking
|
|
70
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
25/02/2022
|
The correction have been made as per the instruction received
|
|
71
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
11/03/2022
|
Jaswant agriculture violation report letter
|
|
72
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
11/03/2022
|
Regarding objection
|
|
73
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
11/03/2022
|
Violation report and Justification
|
|
74
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
12/03/2022
|
Reply by dfo
|
|
75
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
22/03/2022
|
Reply to observations is not uploaded in Part-II
|
|
76
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
22/03/2022
|
Reply to observations is not uploaded in Part-II
|
|
77
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
25/03/2022
|
Objection letter
|
|
78
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
25/03/2022
|
Reply by DFO
|
|
79
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
30/03/2022
|
Reply letter to observation is not uploaded
|
|
80
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
30/03/2022
|
Reply letter to observation is not uploaded
|
|
81
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
06/04/2022
|
Please do reply of EDS
|
|
82
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
22/04/2022
|
The correction have been made as per the instruction received
|
|
83
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
04/05/2022
|
Reply letter of jaswant agri sunam
|
|
84
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
04/05/2022
|
Reply by DFO
|
|
85
|
Nodal Officer
|
REPLY
|
State secretary
|
12/05/2022
|
Reply
|
|
86
|
State secretary
|
REPLY
|
Regional Office
|
12/05/2022
|
reply
|
|
87
|
Regional Office
|
EDS
|
State secretary
|
22/07/2022
|
EDS
|
|
88
|
State secretary
|
EDS
|
Nodal Officer
|
25/07/2022
|
eds
|
|
89
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
25/07/2022
|
eds
|
|
90
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
25/07/2022
|
Regarding objection
|
|
91
|
DFO (Sangrur)
|
EDS
|
User Agency (jaswantagricultureworks1@gmail.com)
|
12/08/2022
|
Please submit documents as instructions given by GOI
|
|
92
|
User Agency (jaswantagricultureworks1@gmail.com)
|
REPLY
|
DFO (Sangrur)
|
23/08/2022
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
23/08/2022
|
Reply of eds letter 23-8-2022
|
|
94
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
24/08/2022
|
Reply by DFO
|
|
95
|
Nodal Officer
|
REPLY
|
State secretary
|
07/09/2022
|
Reply
|
|
96
|
State secretary
|
REPLY
|
Regional Office
|
07/09/2022
|
Reply
|
|
97
|
Regional Office
|
EDS
|
State secretary
|
14/09/2022
|
EDS
|
|
98
|
State secretary
|
EDS
|
Nodal Officer
|
15/09/2022
|
eds
|
|
99
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
15/09/2022
|
eds
|
|
100
|
CF (South Circle)
|
EDS
|
DFO (Sangrur)
|
15/09/2022
|
Regarding objection
|
|
101
|
DFO (Sangrur)
|
REPLY
|
CF (South Circle)
|
28/02/2023
|
Reply of letter
|
|
102
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
28/02/2023
|
Reply by DFO
|
|
103
|
Nodal Officer
|
REPLY
|
State secretary
|
16/03/2023
|
Reply
|
|
104
|
State secretary
|
REPLY
|
Regional Office
|
16/03/2023
|
Reply
|
|