TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/Approach/152046/2022              (ii). Name of Project for which Forest Land is required : M/S TORRENT GAS. PVT.LTD.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.5898 Ha. of Forest Land for approach access road to the Proposed for CNG Station of M/S TORRENT GAS PVT. LTD. on NH-64 (New NH-07) (Patiala to Sangrur Road) at Km. 274.155 (LHS), in Village Wazidpur, Tehsil & Distt - Patiala. Under Forest Division Patiala.              (iv). State : Punjab              (v). Category of the Project : Approach Access              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.5898
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/PB/Approach/152046/202205/02/202215/02/2022  14/02/2022   16/02/2022  15/02/2022   17/02/2022   21/02/2022 Patiala :22/02/2022South Circle:
  29/03/2022 (Patiala)

Punjab:
04/04/2022
Punjab:
13/04/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Punjab) on:27/07/2022  
Query raised by Nodal Officer (Punjab) on:27/07/2022  
Replied by Circle(South Circle) on:12/09/2022  
Query raised by Nodal Officer (Punjab) on:20/09/2022  
Replied by Circle() on:  
Query raised by Circle (South Circle) on:27/07/2022  
Replied by DFO (Patiala) on:12/09/2022  
Query raised by Circle (South Circle) on:20/09/2022  
Replied by DFO () on:  
Query raised by DFO (Patiala) on:24/02/2022  
Replied by UA on :26/02/2022  
Query raised by DFO (Patiala) on:28/07/2022  
Replied by UA on :16/08/2022  
Query raised by DFO (Patiala) on:23/08/2022  
Replied by UA on :24/08/2022  
Query raised by DFO (Patiala) on:18/10/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government .