TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/TRANS/37011/2018   (ii). Name of Project for which Forest Land is required : 220 KV TRANSMISSION LINE FROM EXISTING 220/132/33KV GRID SUBSTATION AT SADEIPALI,BOLANGIR TO PROPOSED 220/132 KV GRID SUB-STATION AT KESINGA.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : In order to impose the quality and reliability of power supply to the District of Kalahandi, Nuapada and Bolangir it is proposed the construct the 220 KV DC .   (iv). State : Orissa   (v). Category of the Project : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 39.196
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/TRANS/37011/201820/11/201824/11/2018   20/05/2019   22/05/2019   31/05/2019 Bolangir :31/05/2019
Kalahandi North :31/05/2019
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Bolangir) on:10/06/2019  
Query raised by DFO (Kalahandi North) on:13/06/2019  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .