TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/Pipeline/123665/2021              (ii). Name of Project for which Forest Land is required : Paradip - Numaligarh Crude Oil Pipeline (PNCPL) Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : NRL is expanding its refining capacity from existing 3.0 MMTPA to 9.0 MMTPA to cater to the growing demand of petroleum products namely Petrol, Diesel, LPG, Kerosene etc. in the Eastern and Northeastern States and parts of West Bengal, Bihar and Jharkhand. The additional crude oil required for t              (iv). State : Orissa              (v). Category of the Project : Pipeline              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 3.347
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/Pipeline/123665/202123/02/202126/02/2021   12/12/2021   14/12/2021   28/12/2021 Rajnagar WL:  29/12/2021
Bhadrak WL:  29/12/2021
Balasore Wildlife:  29/12/2021
Baripada:
  12/10/2022 (Balasore Wildlife)

Bhubaneswar:
  12/10/2022 (Bhadrak WL)

Bhubaneswar:
  12/10/2022 (Rajnagar WL)

Orissa:
15/11/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Balasore Wildlife) on:01/01/2022  
Replied by UA on :13/04/2022  
Query raised by DFO (Bhadrak WL) on:17/01/2022  
Replied by UA on :13/04/2022  
Query raised by DFO (Bhadrak WL) on:16/04/2022  
Replied by UA on :19/04/2022  
Query raised by DFO (Balasore Wildlife) on:25/04/2022  
Replied by UA on :07/06/2022  
Query raised by DFO (Balasore Wildlife) on:13/06/2022  
Replied by UA on :20/06/2022  
NOTE:- Proposal is pending at Nodal Officer .