  (i). Proposal No. : FP/OR/Others/26153/2017   (ii). Name of Project for which Forest Land is required : Land Bank Scheme   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for diversion of 77.333 Ha of forest land under proposed Land Bank Scheme for establishment of downstream aluminium Park in Jharsuguda Tahasil of Jhrasuguda District by M/s IDCO   (iv). State : Orissa   (v). Category of the Project : Others   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Area of forest land proposed for diversion(in ha.): 77.333
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/OR/Others/26153/201712/06/2017aa19/06/2017   20/06/2017 Jharsuguda :20/06/2017
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by DFO (Jharsuguda) on:27/06/2017  
Replied by UA on :20/12/2018  
Query raised by DFO (Jharsuguda) on:21/12/2018  
Replied by UA on :14/02/2019  
Query raised by DFO (Jharsuguda) on:14/02/2019  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .