Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
05/09/2016
|
Compliance as regards deficiencies in the DP
|
|
2
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
10/09/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
11/09/2016
|
Compliance as regards deficiencies in the DP- Submit authenticated maps and documents.
|
|
4
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
15/11/2016
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
29/11/2016
|
Compliance as regards deficiencies in the DP
|
|
6
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
29/11/2016
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
01/12/2016
|
Please submit correct proposed land use plan in concurrence with broken up plan
|
|
8
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
03/12/2016
|
The correction have been made as per the instruction received
|
|
9
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
18/12/2016
|
Please comply with the EDS vide this office Memo No.2819 dtd.18.12.2016
|
|
10
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
19/12/2016
|
Compliance of EDS
|
|
11
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
19/12/2016
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
20/12/2016
|
Compliance submitted
|
|
13
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
27/02/2017
|
Please comply the EDS raised vide memo No. 3855 dated 25.02.2017.
|
|
14
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
06/03/2017
|
Please comply the EDS raised vide Memo No.3854 dtd.25.2.2017 of Addl.PCCF, Nodal
|
|
15
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
08/03/2017
|
Submit the point wise compliance report along with authenticated maps/ documents.
|
|
16
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
10/04/2017
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
10/04/2017
|
Submit the desired point wise compliance report along with authenticated map.
|
|
18
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
11/04/2017
|
Compliance with the EDS raised by Addl.PCCF, Nodal vide Memo No.3855 dtd.25.2.2017
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
27/07/2017
|
Status of ML, authenticated land schedule etc
|
|
20
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
11/08/2017
|
Please comply the EDS vide this office Mem o No. 18009 dated 11.08.2017
|
|
21
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
18/08/2017
|
Please comply the EDS vide Memo No. 18009 dated 11.08.2017 of Addl.PCCF, Nodal
|
|
22
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
18/08/2017
|
Submission of compliance report.
|
|
23
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
29/08/2017
|
Compliance with the EDS raised by Addl.PCCF, Nodal vide Memo No.18009 dtd.11.08.2017
|
|
24
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
25/09/2017
|
Compliance with EDS raised by Special Secretary to Govt. F&E Deptt. vide letter No. 21191 dated 25.09.2017
|
|
25
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
04/10/2017
|
comply
|
|
26
|
Nodal Officer
|
REPLY
|
State secretary
|
04/10/2017
|
Compliance with EDS raised by Special Secretary to Govt. F&E Deptt. vide letter No. 21191 dated 25.09.2017
|
|
27
|
State secretary
|
EDS
|
Nodal Officer
|
12/10/2017
|
discrepancy in the land schedule & land use pattern
|
|
28
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
23/10/2017
|
Please compliance the EDS vide this office Memo No. 22395 dated 20.10.2017.
|
|
29
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
26/10/2017
|
Compliance with the EDS raised by Addl.PCCF, Nodal vide Memo No. 22395 dated 20.10.2017.
|
|
30
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
28/10/2017
|
Please comply the EDS raised by the State Govt.
|
|
31
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
13/11/2017
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
24/01/2018
|
Compliance report
|
|
33
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
28/01/2018
|
Compliance with the EDS raised by Addl.PCCF, Nodal vide Memo No.22395 dtd.20.10.2017
|
|
34
|
Nodal Officer
|
REPLY
|
State secretary
|
06/03/2018
|
Point wise compliance to the EDS raised vide Govt. of Odisha Memo No.21022/F&E dt.12.10.2017 has been sent vide this office Letter No.4334 dt.06.03.2018.
|
|
35
|
Head Office
|
EDS
|
State secretary
|
25/05/2018
|
EDS
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
11/06/2018
|
EDS raised by MoEFCC dated 24.05.2018
|
|
37
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
27/07/2018
|
Please furnish the compliance and the observations of FAC meeting held on 26.04.2018 communicated to you vide this office Memo No.16149 dated 27.07.2018
|
|
38
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
06/08/2018
|
Please furnish the compliance and the observations of FAC meeting held on 26.04.2018 communicated to you vide Memo No.16149 dated 27.07.2018 of Addl.PCCF Nodal, Office of the PCCF, Odisha
|
|
39
|
DFO (Keonjhar)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
24/08/2018
|
Please, comply the deficiencies observed by FAC
|
|
40
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
31/08/2018
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
01/09/2018
|
Please, submit the reply of EDS.
|
|
42
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
10/09/2018
|
Submission of compliance report.
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
16/11/2018
|
Replied.
|
|
44
|
State secretary
|
REPLY
|
Head Office
|
16/11/2018
|
Replied.
|
|