TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/149706/2021              (ii). Name of Project for which Forest Land is required : Diversion of 0.03 Ha forest land involved in Safety Zone Area of Roida II Iron Ore Block for passing through of approach road into the mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.03 Ha forest land involved in Safety Zone Area of Roida II Iron Ore Block for passing through of approach road into the mine              (iv). File no. : 5-ORB552/2023-BHU              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.03
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/OR/MIN/149706/202102/12/202124/01/2022  17/01/2022  05/01/2022  03/12/2021   18/01/2022  17/01/2022  05/01/2022   18/01/2022   19/01/2022 Keonjhar :25/01/2022Rourkela:
  24/01/2023 (Keonjhar)

Orissa:
01/02/2023
Orissa:
20/02/2023
Bhubaneswar:
04/03/2023
28/03/2023
By :Regional Office
Orissa
19/10/2023
23/01/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Keonjhar) on:27/01/2022  
Replied by UA on :01/02/2022  
Query raised by DFO (Keonjhar) on:08/02/2022  
Replied by UA on :23/08/2022  
Query raised by DFO (Keonjhar) on:11/10/2022  
Replied by UA on :14/11/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Bhubaneswar) on:08/11/2023  
Replied by State Government(Orissa) on:02/01/2024  
Query raised by State Government (Orissa) on:20/11/2023  
Replied by Nodal Officer (Orissa) on:27/12/2023  
NOTE:- Stage-II Approval accorded by : Regional Office .