TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MZ/TRANS/142231/2021              (ii). Name of Project for which Forest Land is required : Diversion of 132 kV Kolasib-Aizawl line P&E Mizoram              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 132 kV Kolasib-Aizawl Transmission Line of Power & Electricity dept., Mizoram              (iv). File no. : 3-MZ B 051/2021-SHI              (v). State : Mizoram              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.045
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MZ/TRANS/142231/202112/05/202114/05/2021   17/05/2021   21/05/2021   02/06/2021 Kolasib :02/06/2021Northern circle:
  29/07/2021 (Kolasib)

Mizoram:
30/07/2021
Mizoram:
11/08/2021
Shillong:
16/08/2021
22/08/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:08/10/2021  
Replied by State Government(Mizoram) on:19/05/2022  
Query raised by Regional Office (Shillong) on:06/06/2022  
Replied by State Government(Mizoram) on:12/08/2022  
Query raised by State Government (Mizoram) on:05/01/2022  
Replied by Nodal Officer (Mizoram) on:02/05/2022  
Query raised by State Government (Mizoram) on:16/06/2022  
Replied by Nodal Officer (Mizoram) on:01/08/2022  
Query raised by Nodal Officer (Mizoram) on:05/01/2022  
Replied by Circle(Northern circle) on:30/03/2022  
Query raised by Nodal Officer (Mizoram) on:11/04/2022  
Replied by Circle(Northern circle) on:27/04/2022  
Query raised by Nodal Officer (Mizoram) on:16/06/2022  
Replied by Circle(Northern circle) on:01/07/2022  
Query raised by Nodal Officer (Mizoram) on:08/07/2022  
Replied by Circle(Northern circle) on:01/08/2022  
Query raised by Circle (Northern circle) on:05/01/2022  
Replied by DFO (Kolasib) on:18/02/2022  
Query raised by Circle (Northern circle) on:22/02/2022  
Replied by DFO (Kolasib) on:24/02/2022  
Query raised by Circle (Northern circle) on:25/02/2022  
Replied by DFO (Kolasib) on:11/03/2022  
Query raised by Circle (Northern circle) on:11/03/2022  
Replied by DFO (Kolasib) on:11/03/2022  
Query raised by Circle (Northern circle) on:11/03/2022  
Replied by DFO (Kolasib) on:22/03/2022  
Query raised by Circle (Northern circle) on:30/03/2022  
Replied by DFO (Kolasib) on:30/03/2022  
Query raised by Circle (Northern circle) on:11/04/2022  
Replied by DFO (Kolasib) on:27/04/2022  
Query raised by Circle (Northern circle) on:16/06/2022  
Replied by DFO (Kolasib) on:23/06/2022  
Query raised by Circle (Northern circle) on:23/06/2022  
Replied by DFO (Kolasib) on:24/06/2022  
Query raised by Circle (Northern circle) on:08/07/2022  
Replied by DFO (Kolasib) on:01/08/2022  
Query raised by DFO (Kolasib) on:11/03/2022  
Replied by UA on :19/03/2022  
Query raised by DFO (Kolasib) on:11/04/2022  
Replied by UA on :20/04/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .