TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MZ/ROAD/43622/2019              (ii). Name of Project for which Forest Land is required : Widening and upgradation of NH-54 to 2-Lane with paved shoulder and geometric improvements from Km 8.00 to Km 380.00 in the State of Mizoram (JICA Funded), Km 125.0 to Km 250.0 (Package-2)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The present configuration of road is varying from 3.75m to 5.5 m with earthen shoulder. NH-54 is the lifeline of the State of Mizoram linking its capital Aizawl in northern side at Km 8.00 to Tuipang in southern end at Km 380.00. In this JICA funded project, 372 Km road length is proposed to be wid              (iv). File no. : 3-MZ C 059/2020-SHI              (v). State : Mizoram              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.9856
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MZ/ROAD/43622/201902/01/202007/01/2020   08/01/2020   08/01/2020   09/01/2020

Thenzawl :13/01/2020


Lunglei :13/01/2020

Central circle:
  13/01/2020 (Thenzawl)

Southern circle:
  29/01/2020 (Lunglei)

Mizoram:
20/10/2020
Mizoram:
05/11/2020
Shillong:
05/11/2020
14/06/2022
By :Regional Office
Mizoram
28/06/2023
14/02/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:06/11/2020  
Replied by State Government(Mizoram) on:29/06/2021  
Query raised by Regional Office (Shillong) on:02/08/2021  
Replied by State Government(Mizoram) on:02/02/2022  
Query raised by Regional Office (Shillong) on:14/02/2022  
Replied by State Government(Mizoram) on:15/03/2022  
Query raised by State Government (Mizoram) on:25/11/2020  
Replied by Nodal Officer (Mizoram) on:29/06/2021  
Query raised by State Government (Mizoram) on:25/08/2021  
Replied by Nodal Officer (Mizoram) on:02/02/2022  
Query raised by State Government (Mizoram) on:17/02/2022  
Replied by Nodal Officer (Mizoram) on:10/03/2022  
Query raised by Nodal Officer (Mizoram) on:25/11/2020  
Replied by Circle(Southern circle) on:17/06/2021  
Query raised by Nodal Officer (Mizoram) on:25/11/2020  
Replied by Circle(Central circle) on:29/06/2021  
Query raised by Nodal Officer (Mizoram) on:25/08/2021  
Replied by Circle(Southern circle) on:02/02/2022  
Query raised by Nodal Officer (Mizoram) on:25/08/2021  
Replied by Circle(Central circle) on:02/02/2022  
Query raised by Nodal Officer (Mizoram) on:17/02/2022  
Replied by Circle(Central circle) on:09/03/2022  
Query raised by Nodal Officer (Mizoram) on:17/02/2022  
Replied by Circle(Southern circle) on:09/03/2022  
Query raised by Circle (Southern circle) on:29/01/2020  
Replied by DFO (Lunglei) on:26/05/2020  
Query raised by Circle (Southern circle) on:17/07/2020  
Replied by DFO (Lunglei) on:17/07/2020  
Query raised by Circle (Southern circle) on:20/10/2020  
Replied by DFO (Lunglei) on:20/10/2020  
Query raised by Circle (Southern circle) on:20/10/2020  
Replied by DFO (Lunglei) on:20/10/2020  
Query raised by Circle (Southern circle) on:25/11/2020  
Replied by DFO (Lunglei) on:17/06/2021  
Query raised by Circle (Southern circle) on:25/08/2021  
Replied by DFO (Thenzawl) on:16/12/2021  
Query raised by Circle (Central circle) on:25/08/2021  
Replied by DFO (Lunglei) on:02/02/2022  
Query raised by Circle (Central circle) on:17/02/2022  
Replied by DFO (Thenzawl) on:09/03/2022  
Query raised by Circle (Southern circle) on:17/02/2022  
Replied by DFO (Lunglei) on:09/03/2022  
Query raised by DFO (Lunglei) on:25/11/2020  
Replied by UA on :15/06/2021  
Query raised by DFO (Lunglei) on:09/01/2022  
Replied by UA on :01/02/2022  
Query raised by DFO (Lunglei) on:17/02/2022  
Replied by UA on :03/03/2022  
Query raised by DFO (Thenzawl) on:17/02/2022  
Replied by UA on :03/03/2022  
Query raised by DFO (Lunglei) on:07/03/2022  
Replied by UA on :07/03/2022  
Query raised by DFO (Thenzawl) on:08/03/2022  
Replied by UA on :09/03/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Shillong) on:14/07/2023  
Replied by State Government(Mizoram) on:08/02/2024  
NOTE:- Stage-II Approval accorded by : Regional Office .