Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Lunglei)
|
EDS
|
User Agency (nhidcl.aizawl@gmail.com)
|
28/07/2017
|
I am sending a PDF file for modification of Form- A Part-I. Please make the necessary correction and upload the same early
|
|
2
|
User Agency (nhidcl.aizawl@gmail.com)
|
REPLY
|
DFO (Lunglei)
|
19/09/2017
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Lunglei)
|
EDS
|
User Agency (nhidcl.aizawl@gmail.com)
|
24/09/2017
|
There is something wrong in Part I under serial no.1 such as
Proposal Name
Project Area
Category
Division Name
Area of forest land proposed for diversion
These vital information does not appear in Part II and hence can not proceed.
Please make necessary correction and resubmit at earliest possible.
|
|
4
|
User Agency (nhidcl.aizawl@gmail.com)
|
REPLY
|
DFO (Lunglei)
|
25/09/2017
|
The correction have been made as per the instruction received
|
|