  (i). Proposal No. : FP/MZ/ROAD/139992/2021              (ii). Name of Project for which Forest Land is required : Construction of 2-laning with hard shoulder configuration of NH 302 and NH54 (A) from Lunglei-Tlabung section of NH-302 in the State of Mizoram Under ‘Bharatmala Pariyojana’ on EPC Mode              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 2-laning with hard shoulder configuration of NH 302 and NH54 (A) from Lunglei-Tlabung section of NH-302 in the State of Mizoram Under ‘Bharatmala Pariyojana’ on EPC Mode              (iv). File no. : 3-MZC 024/2022-SHI              (v). State : Mizoram              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 39.81
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MZ/ROAD/139992/202129/03/202121/05/2021   11/09/2021   15/09/2021   19/09/2021

Lunglei :21/09/2021


Tlabung :21/09/2021

Southern circle:
  10/06/2022 (Tlabung)

Southern circle:
  10/06/2022 (Lunglei)

Mizoram:
13/06/2022
Mizoram:
13/06/2022
Shillong:
14/06/2022
30/08/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:17/06/2022  
Replied by State Government(Mizoram) on:20/06/2022  
Query raised by State Government (Mizoram) on:20/06/2022  
Replied by Nodal Officer (Mizoram) on:20/06/2022  
Query raised by Nodal Officer (Mizoram) on:20/06/2022  
Replied by Circle(Southern circle) on:20/06/2022  
Query raised by Circle (Southern circle) on:10/06/2022  
Replied by DFO (Tlabung) on:10/06/2022  
Query raised by Circle (Southern circle) on:10/06/2022  
Replied by DFO (Lunglei) on:12/06/2022  
Query raised by Circle (Southern circle) on:12/06/2022  
Replied by DFO (Tlabung) on:13/06/2022  
Query raised by Circle (Southern circle) on:12/06/2022  
Replied by DFO (Lunglei) on:13/06/2022  
Query raised by Circle (Southern circle) on:20/06/2022  
Replied by DFO (Lunglei) on:20/06/2022  
Query raised by Circle (Southern circle) on:20/06/2022  
Replied by DFO (Tlabung) on:20/06/2022  
Query raised by DFO (Lunglei) on:14/10/2021  
Replied by UA on :27/10/2021  
Query raised by DFO (Lunglei) on:30/11/2021  
Replied by UA on :08/06/2022  
Query raised by DFO (Lunglei) on:08/06/2022  
Replied by UA on :09/06/2022  
Query raised by DFO (Lunglei) on:09/06/2022  
Replied by UA on :09/06/2022  
Query raised by DFO (Lunglei) on:09/06/2022  
Replied by UA on :09/06/2022  
Query raised by DFO (Lunglei) on:13/06/2022  
Replied by UA on :13/06/2022  
Query raised by DFO (Lunglei) on:20/06/2022  
Replied by UA on :20/06/2022  
Query raised by DFO (Lunglei) on:20/06/2022  
Replied by UA on :20/06/2022  