TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MZ/Others/151995/2022              (ii). Name of Project for which Forest Land is required : Retail Outlet (Filling Station)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : It will provide easy access to filling station for the surrounding areas              (iv). File no. : 3-MZ B 041/2022-SHI              (v). State : Mizoram              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.12
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MZ/Others/151995/202204/02/202222/02/2022  18/02/2022   22/02/2022  18/02/2022   04/03/2022   07/03/2022 Mamit :07/03/2022Northern circle:
  04/04/2022 (Mamit)

Mizoram:
01/07/2022
Mizoram:
19/08/2022
Shillong:
02/09/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:27/09/2022  
Query raised by State Government (Mizoram) on:28/09/2022  
Replied by Nodal Officer (Mizoram) on:30/11/2022  
Query raised by Nodal Officer (Mizoram) on:20/07/2022  
Replied by Circle(Northern circle) on:12/08/2022  
Query raised by Nodal Officer (Mizoram) on:06/10/2022  
Replied by Circle(Northern circle) on:21/11/2022  
Query raised by Circle (Northern circle) on:05/05/2022  
Replied by DFO (Mamit) on:05/05/2022  
Query raised by Circle (Northern circle) on:05/05/2022  
Replied by DFO (Mamit) on:05/05/2022  
Query raised by Circle (Northern circle) on:10/05/2022  
Replied by DFO (Mamit) on:27/06/2022  
Query raised by Circle (Northern circle) on:27/06/2022  
Replied by DFO (Mamit) on:27/06/2022  
Query raised by Circle (Northern circle) on:28/06/2022  
Replied by DFO (Mamit) on:28/06/2022  
Query raised by Circle (Northern circle) on:20/07/2022  
Replied by DFO (Mamit) on:08/08/2022  
Query raised by Circle (Northern circle) on:10/08/2022  
Replied by DFO (Mamit) on:11/08/2022  
Query raised by Circle (Northern circle) on:07/10/2022  
Replied by DFO (Mamit) on:21/10/2022  
Query raised by DFO (Mamit) on:20/07/2022  
Replied by UA on :20/07/2022  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .