TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/ROAD/31605/2018              (ii). Name of Project for which Forest Land is required : Mohatara to Harratola Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Road              (iv). State : Madhya Pradesh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.903
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MP/ROAD/31605/201809/03/201825/05/2018  16/04/2018  12/03/2018   13/02/2019  23/05/2018  15/04/2018   15/02/2019   10/06/2019 Shahdol South(T) :11/06/2019Shahdol(T):
  12/09/2022 (Shahdol South(T))

Madhya Pradesh:
10/10/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Madhya Pradesh) on:31/10/2022  
Query raised by Circle (Shahdol(T)) on:31/10/2022  
Query raised by DFO (Shahdol South(T)) on:18/06/2019  
Replied by UA on :15/07/2019  
Query raised by DFO (Shahdol South(T)) on:20/08/2019  
Replied by UA on :22/01/2020  
Query raised by DFO (Shahdol South(T)) on:01/02/2020  
Replied by UA on :30/03/2022  
Query raised by DFO (Shahdol South(T)) on:01/04/2022  
Replied by UA on :19/04/2022  
Query raised by DFO (Shahdol South(T)) on:09/05/2022  
Replied by UA on :23/06/2022  
Query raised by DFO (Shahdol South(T)) on:18/07/2022  
Replied by UA on :12/09/2022  
NOTE:- Proposal is pending at DFO due to EDS raised by Nodal Officer .