Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand898@gmail.com)
|
15/06/2022
|
Demand Note
|
|
2
|
User Agency (pariharanand898@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
18/07/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
21/10/2022
|
Nodal Officer letter dt. 21/10/2022 enclosed.
|
|
4
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
21/10/2022
|
Nodal Officer letter dt. 21/10/2022 enclosed.
|
|
5
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
05/04/2023
|
CA Plantation Scheme
|
|
6
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
05/04/2023
|
CA Plantation Scheme
|
|
7
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
18/05/2023
|
Nodal Officer letter dt. 18/05/2023 enclosed.
|
|
8
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
18/05/2023
|
Nodal Officer letter dt. 18/05/2023 enclosed.
|
|
9
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
18/05/2023
|
Nodal Officer letter dt. 18/05/2023 enclosed.
|
|
10
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
24/05/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
26/05/2023
|
CA project has been uploaded online.
|
|
12
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
26/05/2023
|
Further detail send by DFO North Balaghat
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
03/10/2023
|
EDS letter on 3.10.2023
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
05/10/2023
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
05/10/2023
|
Nodal Officer letter dt. 05/10/2023 enclosed.
|
|
16
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
05/10/2023
|
Nodal Officer letter dt. 05/10/2023 enclosed.
|
|
17
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
05/10/2023
|
Nodal Officer letter dt. 05/10/2023 enclosed.
|
|
18
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
13/10/2023
|
The correction have been made as per the instruction received
|
|
19
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
20/10/2023
|
10 points of information received by the applicant department.
|
|
20
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
20/10/2023
|
Forwarded
|
|
21
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
26/10/2023
|
|
|
22
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
26/10/2023
|
|
|
23
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
26/10/2023
|
|
|
24
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
21/11/2023
|
The correction have been made as per the instruction received
|
|
25
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
24/11/2023
|
Lt. No. 4739 dt. 23.10.2023. Information regarding point number 6.
|
|
26
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
29/11/2023
|
Forwarded
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
06/12/2023
|
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
06/12/2023
|
Nodal Officer letter dt. 06-12-2023 enclosed.
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
28/12/2023
|
EDS letter on 27.12.2023
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
15/01/2024
|
|
|
31
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
15/01/2024
|
Nodal Officer letter dt. 15/01/2024 enclosed.
|
|
32
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
15/01/2024
|
Nodal Officer letter dt. 15/01/2024 enclosed.
|
|
33
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
19/01/2024
|
According to point number 3 and 4 is required.
|
|
34
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
20/01/2024
|
The correction have been made as per the instruction received
|
|
35
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
23/01/2024
|
Correct - CA and RDF KML
|
|
36
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
24/01/2024
|
The correction have been made as per the instruction received
|
|
37
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
26/01/2024
|
Correct KML RDF
|
|
38
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
26/01/2024
|
The correction have been made as per the instruction received
|
|
39
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
26/01/2024
|
Reply - Letter No. 281 Dt. 15.01.2024
|
|
40
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
28/01/2024
|
Lt. No. 120 Dt. 27.01.2024
|
|
41
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
30/01/2024
|
|
|
42
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
30/01/2024
|
|
|
43
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
31/01/2024
|
correct KML of Road
|
|
44
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
31/01/2024
|
The correction have been made as per the instruction received
|
|
45
|
DFO (North Balaghat)
|
EDS
|
User Agency (pariharanand2561@gmail.com)
|
31/01/2024
|
Correct Toposheet
|
|
46
|
User Agency (pariharanand2561@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
31/01/2024
|
The correction have been made as per the instruction received
|
|
47
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
01/02/2024
|
Update KML, toposheet, DFO Certificate, map and Letter No. 281 dt. 15.01.2024, Point No. -2 CF Inspection Report.
|
|
48
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
01/02/2024
|
Ltt. No. 133 Dt. 30-01-2024 with CF Site Inspection report
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
01/04/2024
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
01/04/2024
|
|
|