TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/IRRIG/36231/2018              (ii). Name of Project for which Forest Land is required : Morand-Ganjal Irrigation Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Morand and Ganjal Complex project is a major irrigation project included in the Narmada Masterplan, its sub basin is one of the major sub basins of the Narmada River in its ‘Middle Zone’. The proposed project envisages construction of two dams, one across Morand River and another across Ganjal River              (iv). State : Madhya Pradesh              (v). Category of the Project : Irrigation              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 2285.91
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR)Stage-I Approval onStage-II Approval on
FP/MP/IRRIG/36231/201803/11/201822/02/2019  04/12/2018  09/11/2018   22/02/2019  20/02/2019  01/12/2018   22/02/2019   06/03/2019 Hoshangabad(T) :11/03/2019
Betul North(T) :11/03/2019
West Betul :11/03/2019
Harda(T) :11/03/2019
Khandwa(T) :11/03/2019
Betul(T):
  24/03/2022 (West Betul)

Betul(T):
  22/07/2022 (Betul North(T))

Hoshangabad(T):
  14/05/2019 (Harda(T))

Khandwa(T):
  14/05/2019 (Khandwa(T))

Hoshangabad(T):
  17/05/2019 (Hoshangabad(T))

Madhya Pradesh:
01/08/2022
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Circle (Hoshangabad(T)) on:07/11/2022  
Query raised by Circle (Hoshangabad(T)) on:07/11/2022  
Query raised by DFO (Khandwa(T)) on:18/03/2019  
Replied by UA on :30/03/2019  
Query raised by DFO (West Betul) on:24/09/2019  
Replied by UA on :05/10/2021  
Query raised by DFO (Betul North(T)) on:05/10/2021  
Replied by UA on :05/10/2021  
Query raised by DFO (Betul North(T)) on:06/10/2021  
Replied by UA on :06/10/2021  
Query raised by DFO (West Betul) on:06/10/2021  
Replied by UA on :06/10/2021  
Query raised by DFO (Betul North(T)) on:30/11/2021  
Replied by UA on :27/01/2022  
Query raised by DFO (West Betul) on:29/12/2021  
Replied by UA on :  
Query raised by DFO (Hoshangabad(T)) on:21/11/2022  
Query raised by DFO (Harda(T)) on:21/11/2022  
NOTE:- Proposal is pending at User Agency due to EDS raised by CF .