TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/IRRIG/32637/2018              (ii). Name of Project for which Forest Land is required : Garawadiya Tank Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Garawadiya Tank is situated at village Garawadiya tehsil Rawti district Ratlam. The construction of Garawadiya Tank is essential to required 12.77 Ha. forest land are compartment NO. PF36 area is 5.63 Ha. and PF37 area is 7.14 Ha.              (iv). File no. : 6-MPC080/2018-BHO              (v). State : Madhya Pradesh              (vi). Category of the Project : Irrigation              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 12.77
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MP/IRRIG/32637/201820/03/201808/05/2018  03/05/2018  09/04/2018  02/04/2018  23/03/2018   09/05/2018  04/05/2018  03/05/2018  09/04/2018  31/03/2018   11/05/2018   29/06/2018 Ratlam(T) :30/06/2018Ujjain(T):
  29/09/2018 (Ratlam(T))

Madhya Pradesh:
08/10/2018
Madhya Pradesh:
23/10/2018
Bhopal:
30/11/2018
22/01/2019
By :Regional Office
Madhya Pradesh
26/02/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhopal) on:28/12/2018  
Replied by State Government(Madhya Pradesh) on:29/12/2018  
Query raised by State Government (Madhya Pradesh) on:29/12/2018  
Replied by Nodal Officer (Madhya Pradesh) on:29/12/2018  
Query raised by Nodal Officer (Madhya Pradesh) on:29/12/2018  
Replied by Circle(Ujjain(T)) on:29/12/2018  
Query raised by Circle (Ujjain(T)) on:29/12/2018  
Replied by DFO (Ratlam(T)) on:29/12/2018  
Query raised by DFO (Ratlam(T)) on:07/07/2018  
Replied by UA on :14/07/2018  
Query raised by DFO (Ratlam(T)) on:02/08/2018  
Replied by UA on :04/08/2018  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Bhopal) on:12/04/2024  
Replied by State Government(Madhya Pradesh) on:04/04/2025  
NOTE:- Proposal is pending at RO for Stage-II .