  (i). Proposal No. : FP/MN/ROAD/151400/2022              (ii). Name of Project for which Forest Land is required : Widening and improvement of Package - II of Imphal-Jiribam Road Section of NH-37 (NH-53) into two laning of existing 15+946 km to 33+395 km in the State of Manipur by NHIDCL              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Widening and improvement of Package - II of Imphal-Jiribam Road Section of NH-37 (NH-53) into two laning of existing 15+945 km to 33+395 km in the State of Manipur by NHIDCL              (iv). State : Manipur              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 17.91
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MN/ROAD/151400/202221/01/202221/01/2022   21/01/2022   28/01/2022   04/02/2022 Bishnupur Forest Division,Bishnupur:  10/02/2022
Northern Forest Division,Ktuigpokpi:  10/02/2022
Noney forest division:  10/02/2022
Southern Forest Circle:
  14/03/2022 (Bishnupur Forest Division,Bishnupur)

Western Forest Circle:
  23/03/2022 (Noney forest division)

Northern Forest Circle:
  23/03/2022 (Northern Forest Division,Ktuigpokpi)

Manipur:
18/05/2022
Manipur:
19/07/2022
Shillong:
03/08/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:12/08/2022  
Query raised by State Government (Manipur) on:27/07/2022  
Replied by Nodal Officer (Manipur) on:03/08/2022  
Query raised by Nodal Officer (Manipur) on:27/07/2022  
Replied by Circle(Western Forest Circle) on:01/08/2022  
Query raised by Nodal Officer (Manipur) on:01/08/2022  
Replied by Circle(Western Forest Circle) on:02/08/2022  
Query raised by Circle (Northern Forest Circle) on:24/03/2022  
Replied by DFO (Northern Forest Division,Ktuigpokpi) on:24/03/2022  
Query raised by Circle (Western Forest Circle) on:25/03/2022  
Replied by DFO (Noney forest division) on:25/03/2022  
Query raised by Circle (Western Forest Circle) on:28/07/2022  
Replied by DFO (Noney forest division) on:01/08/2022  
Query raised by Circle (Western Forest Circle) on:02/08/2022  
Replied by DFO (Noney forest division) on:02/08/2022  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .