  (i). Proposal No. : FP/MH/MIN/144023/2021              (ii). Name of Project for which Forest Land is required : Renewal of Forest Clearance of 0.55 Ha. at Gumgaon Mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : MoEF, F.C. Division, Bhopal has granted the formal approval of diversion of forest land for mining activity vide letter no. 8-C/5/605/98-FCW/1616, dtd. 16.07.2003. MOIL has carried our exploration work over the entire area by total 24 bore holes out of which one bore holes within in forest l              (iv). State : Maharashtra              (v). Category of the Project : Mining              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.55
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onStage-II Approval on
FP/MH/MIN/144023/202125/06/2021aa25/06/2021   29/06/2021 Nagpur :29/06/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Nagpur) on:02/02/2022  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .