TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/TRANS/26229/2017              (ii). Name of Project for which Forest Land is required : TRANSMISSION LINE              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : CONSTRUCTING 200MTR 11KV OH LINE              (iv). State : Kerala              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.06
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/TRANS/26229/201718/05/201721/06/2017  16/06/2017   29/06/2017  21/06/2017   10/07/2017   09/08/2017 Thiruvananthapuram :10/08/2017
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Thiruvananthapuram) on:04/02/2022  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .