TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/ROAD/42244/2019              (ii). Name of Project for which Forest Land is required : Six laning of Vadakkenchery - Thrissur section of NH 544              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Ministry of Road Transport & Highways(MoRTH), Government of India has decided to take up various National Highway Corridors for augmentation capacity for safe and efficient movement of traffic by strengthening and upgrading to required width. National Highways Authority of India has been entrusted t              (iv). File no. : F.No.4-KLB1220/2019-BAN              (v). State : Kerala              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.4318
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/ROAD/42244/201926/09/2019aa27/09/2019   30/09/2019

Thrissur :30/09/2019


Peechi Wildlife Sanctuary :30/09/2019

Central circle, Thrissur:
  01/10/2019 (Thrissur)

Palakkad Field Director Parambikulam Tiger Reseve:
  01/10/2019 (Peechi Wildlife Sanctuary)

Kerala:
10/10/2019
Kerala:
08/11/2019
Bangalore:
03/12/2019
31/01/2020
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:27/12/2019  
Replied by State Government(Kerala) on:25/01/2020  
Query raised by State Government (Kerala) on:06/01/2020  
Replied by Nodal Officer (Kerala) on:25/01/2020  
Query raised by Nodal Officer (Kerala) on:08/01/2020  
Replied by Circle(Palakkad Field Director Parambikulam Tiger Reseve) on:25/01/2020  
Query raised by Circle (Central circle, Thrissur) on:02/10/2019  
Replied by DFO (Thrissur) on:02/10/2019  
Query raised by Circle (Central circle, Thrissur) on:02/10/2019  
Replied by DFO (Thrissur) on:02/10/2019  
Query raised by Circle (Palakkad Field Director Parambikulam Tiger Reseve) on:08/01/2020  
Query raised by DFO (Peechi Wildlife Sanctuary) on:08/01/2020  
Replied by UA on :18/01/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .