Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Munnar)
|
EDS
|
User Agency (pmthep@hotmail.com)
|
09/07/2020
|
Query - Thottiyar Power evacuation - 1.225 Ha.
|
|
2
|
User Agency (pmthep@hotmail.com)
|
REPLY
|
DFO (Munnar)
|
01/12/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Munnar)
|
EDS
|
User Agency (pmthep@hotmail.com)
|
03/05/2021
|
Query - Thottiyar Power evacuation about 0.7945 Ha
|
|
4
|
User Agency (pmthep@hotmail.com)
|
REPLY
|
DFO (Munnar)
|
05/05/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (High Range Circle, Kottayam)
|
EDS
|
DFO (Munnar)
|
04/06/2021
|
1. User agency to identify and give details of equal non-forest land as compensatory land. Revenue puramboke land is already available for transfer in Chinnakanal village.
2.Divisional forest Officer to upload the details of compensatory afforestation scheme including Survey skecth, kml file, SSP and financial forecast.
|
|
6
|
DFO (Munnar)
|
REPLY
|
CF (High Range Circle, Kottayam)
|
06/07/2021
|
Reply to EDS on 04.06.2021
|
|
7
|
CF (High Range Circle, Kottayam)
|
EDS
|
DFO (Munnar)
|
26/08/2021
|
Please update the CA details furnished , alongwith connected .kmlfiles
|
|
8
|
DFO (Munnar)
|
REPLY
|
CF (High Range Circle, Kottayam)
|
27/08/2021
|
CA details updated and resubmitted
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
13/10/2021
|
Compliance report of earlier diversion of Thottiyar Project, Kml file of the CA land, Status of encroachment, etc.
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
03/11/2021
|
essential details
|
|
11
|
Nodal Officer
|
EDS
|
CF (High Range Circle, Kottayam)
|
10/11/2021
|
Please upload CA land details
|
|
12
|
CF (High Range Circle, Kottayam)
|
EDS
|
DFO (Munnar)
|
12/11/2021
|
Please upload CA land details
|
|
13
|
DFO (Munnar)
|
REPLY
|
CF (High Range Circle, Kottayam)
|
12/11/2021
|
The essential details called for are updated. KML file of compensatory land in Chinnakanal is sent by e-mail
|
|
14
|
CF (High Range Circle, Kottayam)
|
REPLY
|
Nodal Officer
|
12/11/2021
|
The details are submitted herewith. kml format of compensatory afforestation land at Chinnakanal is sent via e-mail seperately
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
15/11/2021
|
Reply to the querries submitted vide FC2-27267/2018 dated 05.11.2021
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
15/11/2021
|
compliance report recommended and forwarded
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
01/12/2021
|
REC considered the proposal in its meeting held on 23/11/2021 and decided to request the SG to furnish whether the existing 66 KV can be upgraded to 220 KV for evacuation of the power from the Hydel Project, possibility of laying underground 220 KV either completely or partially etc.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
30/12/2021
|
Reply to EDS by MoEF
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
08/02/2022
|
Map., Survey sketch, Google Earth Map and FRA Certificate are attached
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
15/02/2022
|
Map, sketch and FRA certificate
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
24/02/2022
|
Information sought vide this office letter dtd 30.11.2021 not furnished.
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
04/03/2022
|
for furnishing the details sought
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
04/03/2022
|
The details of KSEBL is furnished
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
19/03/2022
|
kindly consider the enclosure for further processing of the proposal. The inconvenience caused may be condoned.
|
|