Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Cauvery Wildlife)
|
EDS
|
User Agency (eeemwdrmg@yahoo.com)
|
29/05/2018
|
Land for CA Compensatory Afforestation shall be provided by UA for the forest land diverted.
|
|
2
|
User Agency (eeemwdrmg@yahoo.com)
|
REPLY
|
DFO (Cauvery Wildlife)
|
21/12/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Cauvery Wildlife)
|
EDS
|
User Agency (eeemwdrmg@yahoo.com)
|
29/05/2019
|
I have inspected the proposed area Chilandawadi Reserve forest of Sangama Wildlife Range On 13.05.2019 in view of diversion of said forest area to lay the transmission line form Doddalahalli station to Hegganuru village. The proposed area consist of the species like Azadicarachta indica, Albizia amara, Cassia siamea, Acacia Catechu, Acacia Ferruginea, Diospyros Candolleana Etc. and were Enumerated and marked with paints. The proposed area is a linear stretch of 18mtr of width and 1.20Kms of length. And requirement of forest land proposed by the user agency is unavailable and barest minimum and passing all along the road
|
|
4
|
User Agency (eeemwdrmg@yahoo.com)
|
REPLY
|
DFO (Cauvery Wildlife)
|
30/05/2019
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Chamarajanagara)
|
20/11/2019
|
Copy of letter for the correction have been made as per the instruction received
|
|
6
|
CF (Chamarajanagara)
|
EDS
|
DFO (Cauvery Wildlife)
|
27/11/2019
|
.
|
|
7
|
DFO (Cauvery Wildlife)
|
REPLY
|
CF (Chamarajanagara)
|
02/12/2019
|
Hulthar beat CA Scheme details
|
|
8
|
CF (Chamarajanagara)
|
REPLY
|
Nodal Officer
|
12/12/2019
|
CA schemes documents uploaded.
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
07/02/2020
|
please send link properly. it is not available in recommendation category. only eds available.
|
|
10
|
Nodal Officer
|
EDS
|
CF (Chamarajanagara)
|
29/02/2020
|
Copy of the letter uploaded in this portal
|
|
11
|
CF (Chamarajanagara)
|
EDS
|
DFO (Cauvery Wildlife)
|
05/03/2020
|
.
|
|
12
|
DFO (Cauvery Wildlife)
|
EDS
|
User Agency (eeemwdrmg@yahoo.com)
|
10/03/2020
|
Submit the Essential documents and Three ink-signed sets upload on FC web Portal
|
|
13
|
User Agency (eeemwdrmg@yahoo.com)
|
REPLY
|
DFO (Cauvery Wildlife)
|
11/03/2020
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Cauvery Wildlife)
|
EDS
|
User Agency (eeemwdrmg@yahoo.com)
|
04/05/2020
|
Please upload the proposal As per PCCF letetr dated 20.04.2020
|
|
15
|
User Agency (eeemwdrmg@yahoo.com)
|
REPLY
|
DFO (Cauvery Wildlife)
|
05/05/2020
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Cauvery Wildlife)
|
REPLY
|
CF (Chamarajanagara)
|
21/05/2020
|
The Route 1 Proposed by the user agency may be accepted with maximum suitable height for providing path way for the elephant and wildlife
|
|
17
|
DFO (Cauvery Wildlife)
|
REPLY
|
CF (Chamarajanagara)
|
21/05/2020
|
The Route 1 Proposed by the user agency may be accepted with maximum suitable height for providing path way for the elephant and wildlife
|
|
18
|
CF (Chamarajanagara)
|
REPLY
|
Nodal Officer
|
10/06/2020
|
The recommendation by the DCF, Cauvery Wildlife Division may be considered.
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
04/09/2020
|
reply to gok quary
|
|
20
|
Regional Office
|
EDS
|
State secretary
|
19/11/2020
|
Clearance from Standing Committee on NBWL as the project farms a part of Cauvery WLS.
|
|
21
|
State secretary
|
EDS
|
Nodal Officer
|
01/01/2021
|
Please furnish information to eds raised by MoEF vide letter dated 19-11-2020
|
|
22
|
Nodal Officer
|
EDS
|
CF (Chamarajanagara)
|
05/01/2021
|
The GOI vide letter F.No 4-KRB 1225/2020-BAN/884 Dated 19-11-2020 has sought clearance from the Standing Committee of the NBWL. As verified from the Timeline on Wildlife Clearance Web Portal www.parivesh.nic.in, the Wildlife Proposal is presently pending with SBWL State Board for Wildlife. As the FC proposal is not pending with Nodal Officer, the online link is transferred herewith to GOK for further needful. Copy of the Timeline taken from the Wildlife Clearance Web Portal is enclosed for ready reference.
|
|
23
|
CF (Chamarajanagara)
|
REPLY
|
Nodal Officer
|
05/01/2021
|
.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
05/01/2021
|
The GOI vide letter F.No 4-KRB 1225/2020-BAN/884 Dated 19-11-2020 has sought clearance from the Standing Committee of the NBWL. As verified from the Timeline on Wildlife Clearance Web Portal www.parivesh.nic.in, the Wildlife Proposal is presently pending with SBWL State Board for Wildlife. As the FC proposal is not pending with Nodal Officer, the online link is transferred herewith to GOK for further needful. Copy of the Timeline taken from the Wildlife Clearance Web Portal is enclosed for ready reference.
|
|
25
|
State secretary
|
EDS
|
Nodal Officer
|
07/07/2021
|
sought information from PCCF
|
|
26
|
Nodal Officer
|
EDS
|
CF (Chamarajanagara)
|
09/08/2021
|
EDS
|
|
27
|
CF (Chamarajanagara)
|
EDS
|
DFO (Cauvery Wildlife)
|
06/12/2021
|
For Rejection
|
|
28
|
DFO (Cauvery Wildlife)
|
EDS
|
User Agency (eeemwdrmg@yahoo.com)
|
13/12/2021
|
Attend the Observation as per PCCF Wildiife letter
|
|
29
|
User Agency (eeemwdrmg@yahoo.com)
|
REPLY
|
DFO (Cauvery Wildlife)
|
19/01/2022
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Cauvery Wildlife)
|
EDS
|
User Agency (eeemwdrmg@yahoo.com)
|
21/01/2022
|
attend
|
|
31
|
User Agency (eeemwdrmg@yahoo.com)
|
REPLY
|
DFO (Cauvery Wildlife)
|
24/01/2022
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Cauvery Wildlife)
|
REPLY
|
CF (Chamarajanagara)
|
16/05/2022
|
Principal Chief Conservator of Forests and Chief Wildlife Warden vide letter No. KFD/WL/Land(NBW)/1/2020 dated 15-03-2022 to BTCF Account as a compliance to approved Mitigation Plan
|
|
33
|
CF (Chamarajanagara)
|
REPLY
|
Nodal Officer
|
14/06/2022
|
Proposal may be approved.
|
|
34
|
Nodal Officer
|
EDS
|
CF (Chamarajanagara)
|
29/06/2022
|
EDS
|
|
35
|
CF (Chamarajanagara)
|
EDS
|
DFO (Cauvery Wildlife)
|
17/08/2022
|
For obtained and submit NBWL approval copy from UA.
|
|