Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
15/02/2018
|
Re submit the proposal
|
|
2
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
23/02/2018
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Mysore)
|
05/12/2018
|
Proposal found incomplete as per the enclosed letter. Please upload the same
|
|
4
|
CF (Mysore)
|
EDS
|
DFO (Mandya)
|
11/12/2018
|
Pl correct as per PCCF letter.
|
|
5
|
DFO (Mandya)
|
REPLY
|
CF (Mysore)
|
28/01/2019
|
please rectify deficiencies
|
|
6
|
CF (Mysore)
|
EDS
|
DFO (Mandya)
|
28/01/2019
|
Submit PCCF, Bangalore let dt.
|
|
7
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
31/01/2019
|
Please Provide details as per the PCCF, let. dt. 04-12-2018.
|
|
8
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
06/02/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
11/02/2019
|
user agency has submitted essential details
|
|
10
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
11/02/2019
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
11/02/2019
|
the user agency has submitted essential details
|
|
12
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
11/02/2019
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
13/02/2019
|
The user agency has submitted essential details
|
|
14
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
16/02/2019
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
25/03/2019
|
the user agency have been made as per the instruction recieved
|
|
16
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
04/04/2019
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
20/04/2019
|
user agency have been submitted Essential details
|
|
18
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
02/05/2019
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Mandya)
|
REPLY
|
CF (Mysore)
|
28/06/2019
|
EDS Attended
|
|
20
|
CF (Mysore)
|
REPLY
|
Nodal Officer
|
29/06/2019
|
Objection attended as per PCCF Letter 11-12-2018.
|
|
21
|
CF (Mysore)
|
REPLY
|
Nodal Officer
|
29/06/2019
|
Objection attended as per PCCF Letter 11-12-2018.
|
|
22
|
Regional Office
|
EDS
|
State secretary
|
20/01/2021
|
Alternatives examined, certificate regarding non availability of revenue land etc
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
12/02/2021
|
eds sought
|
|
24
|
Nodal Officer
|
EDS
|
CF (Mysore)
|
12/02/2021
|
pls reply to query raised by GOI
|
|
25
|
CF (Mysore)
|
EDS
|
DFO (Mandya)
|
10/03/2021
|
Providing details as per the PCCF letter
|
|
26
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
17/03/2021
|
User agency has provided essential details as per APCCF FC and Nodal Officer FCA direction.
|
|
27
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
06/07/2021
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
23/07/2021
|
User agency has provided essential details as per APCCF FC and Nodal Officer FCA direction.
|
|
29
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
23/07/2021
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Mandya)
|
EDS
|
User Agency (tswoppura@gmail.com)
|
18/09/2021
|
User agency has provided essential details as per APCCF FC and Nodal Officer FCA direction.
|
|
31
|
User Agency (tswoppura@gmail.com)
|
REPLY
|
DFO (Mandya)
|
18/09/2021
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Mandya)
|
REPLY
|
CF (Mysore)
|
27/09/2021
|
User agency has provided essential details as per APCCF FC and Nodal Officer FCA direction.
|
|
33
|
CF (Mysore)
|
EDS
|
DFO (Mandya)
|
05/01/2022
|
Letter Enclosed
|
|
34
|
DFO (Mandya)
|
REPLY
|
CF (Mysore)
|
05/01/2022
|
submitted
|
|
35
|
CF (Mysore)
|
REPLY
|
Nodal Officer
|
05/01/2022
|
letter enclosed
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
10/01/2022
|
EDS reply submitted by UA
|
|
37
|
State secretary
|
REPLY
|
Regional Office
|
19/02/2022
|
eds
|
|
38
|
Regional Office
|
EDS
|
State secretary
|
25/02/2022
|
Requested to furnish the certificate of District Collector regarding the non availability of revenue land for the project.
|
|
39
|
State secretary
|
EDS
|
Nodal Officer
|
07/03/2022
|
eds
|
|
40
|
Nodal Officer
|
EDS
|
CF (Mysore)
|
18/03/2022
|
EDS
|
|
41
|
CF (Mysore)
|
EDS
|
DFO (Mandya)
|
19/07/2022
|
DC Mandy copy enclosed
|
|
42
|
DFO (Mandya)
|
REPLY
|
CF (Mysore)
|
19/07/2022
|
Mandya dc copy enclosed
|
|
43
|
CF (Mysore)
|
REPLY
|
Nodal Officer
|
19/07/2022
|
Certificate of the non availability of Govt land in Pandavapura Town other than Sy No. 10 of DC Mandya is attached
|
|
44
|
Nodal Officer
|
REPLY
|
State secretary
|
04/08/2022
|
Reply to EDS
|
|
45
|
State secretary
|
REPLY
|
Regional Office
|
13/09/2022
|
EDS
|
|