TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/Others/25957/2017              (ii). Name of Project for which Forest Land is required : Laying of OFC Cable Under Central Govt. NOFN Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Trenching and laying the Optical Fiber Cable under NOFN Project (Digital India) to the Gram Panchayats 1) Konchavaram 2)Shadipur 3) Venkatapur villages of Chincholi Taluk of Gulbarga(Dist) for providing high speed Broadband connections for E-Governance and Other Telecom facilities through OFC. No              (iv). File no. : FEE 4 FLL 2019 e              (v). State : Karnataka              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.9215
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/Others/25957/201702/05/201704/06/2018  07/04/2018  02/11/2017  05/06/2017  10/05/2017   15/06/2018  09/05/2018  09/03/2018  23/09/2017  20/05/2017   07/07/2018   28/08/2018 Gulbarga :03/09/2018Gulbarga:
  07/03/2019 (Gulbarga)

Karnataka:
27/03/2019
Karnataka:
18/06/2019
Bangalore:
07/11/2020
16/09/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Karnataka) on:20/08/2019  
Replied by Nodal Officer (Karnataka) on:17/03/2020  
Query raised by Nodal Officer (Karnataka) on:31/10/2019  
Replied by Circle(Gulbarga) on:03/03/2020  
Query raised by Circle (Gulbarga) on:12/03/2019  
Replied by DFO (Gulbarga) on:14/03/2019  
Query raised by Circle (Gulbarga) on:20/11/2019  
Replied by DFO (Gulbarga) on:24/02/2020  
Query raised by DFO (Gulbarga) on:10/10/2018  
Replied by UA on :26/10/2018  
Query raised by DFO (Gulbarga) on:01/12/2018  
Replied by UA on :09/01/2019  
Query raised by DFO (Gulbarga) on:24/01/2019  
Replied by UA on :23/02/2019  
Query raised by DFO (Gulbarga) on:27/11/2019  
Replied by UA on :18/02/2020  
NOTE:- Proposal is pending at Pending at DFO for verifying Compliance of Conditions .