TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/MIN/6858/2014   (ii). Name of Project for which Forest Land is required : Diversion of additional area over and extent of 159.01ha (Originally 167.63ha.)area of forest land for KUMARASWAMY IRON ORE MINE, in ML No.1111, NMDC LTD, DIST- BALLARI, KARNATAKA.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Kumaraswamy Iron Ore Mine is situated in Bellary district of Karnataka State. This Mine has a valid Mining Lease Area of 647.5 Ha in the Kumaraswamy forest range of Bellary-Hospet Iron Ore belt. Out of this 155.17 Ha is revenue area and the balance area of 492.33 Ha is the forest area. As per Mo   (iv). State : Karnataka   (v). Category of the Project : Mining   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Area of forest land proposed for diversion(in ha.): 159.01
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR)Stage-I Approval onStage-II Approval on
FP/KA/MIN/6858/201403/09/201426/09/2014  22/09/2014  10/09/2014   26/09/2014  24/09/2014  13/09/2014   01/10/2014   29/10/2014 Bellary :16/12/2014Bellary:
  11/09/2019 (Bellary)

Karnataka:
23/09/2019
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by DFO (Bellary) on:31/01/2015  
Replied by UA on :10/03/2015  
Query raised by DFO (Bellary) on:14/05/2015  
Replied by UA on :25/05/2015  
Query raised by DFO (Bellary) on:03/04/2016  
Replied by UA on :09/06/2016  
Query raised by DFO (Bellary) on:23/07/2016  
Replied by UA on :11/08/2016  
Query raised by DFO (Bellary) on:09/12/2016  
Replied by UA on :14/12/2016  
Query raised by DFO (Bellary) on:21/11/2017  
Replied by UA on :09/12/2017  
Query raised by DFO (Bellary) on:13/03/2018  
Replied by UA on :19/04/2018  
Query raised by DFO (Bellary) on:16/07/2018  
Replied by UA on :21/07/2018  
NOTE:- Proposal is pending at Nodal Officer .