Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
24/02/2022
|
Sir, please do the necessary corrections as per EDS
|
|
2
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (abhngh.761l@gov.in)
|
02/03/2022
|
sir, Please do the necessary corrections as per EDS
|
|
3
|
User Agency (abhngh.761l@gov.in)
|
REPLY
|
DFO (J.V.Forest Division)
|
26/04/2022
|
The correction have been made as per the instruction received
|
|
4
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (abhngh.761l@gov.in)
|
27/04/2022
|
The information submitted by User Agency is incompleted
|
|
5
|
User Agency (abhngh.761l@gov.in)
|
REPLY
|
DFO (J.V.Forest Division)
|
30/04/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
24/06/2022
|
The short comings of the case file has been cleared
|
|
7
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
14/07/2022
|
Please upload the requisite documents
|
|
8
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
14/07/2022
|
Please upload the requisite documents.
|
|
9
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (abhngh.761l@gov.in)
|
18/07/2022
|
The EDs raised by Adl. Pr. CCF , Link Officer FCA vide his NoPCCF/FCA/3393/2106-08 datred14-07-2022
|
|
10
|
User Agency (abhngh.761l@gov.in)
|
REPLY
|
DFO (J.V.Forest Division)
|
04/08/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
06/09/2022
|
The Correction has been made as per instructions received
|
|
12
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
10/09/2022
|
The User Agency and DFO JV are requested to do the necessary corrections as mentioned under:-
1- User Agency need to upload authenticated coloured layout plan of the project.
2- DFO need to upload correct SOI-Topo Sheet under column 13 Serial No. iv indicating the CA site.
3- DFO need to upload the specific recommendation as per the format, as already circulated with you
|
|
13
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (abhngh.761l@gov.in)
|
10/09/2022
|
The EDs raised by Worthy Conservator of Forests Kashmir North Circle Sopore User Agency are requested to do the necessary corrections, User Agency need to upload authenticated colored layout plan of the project
|
|
14
|
User Agency (abhngh.761l@gov.in)
|
REPLY
|
DFO (J.V.Forest Division)
|
17/09/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
20/09/2022
|
The correction has been made as per instructions received by worthy CF North Circle Sopore
|
|
16
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
21/09/2022
|
The UA and DFO concerned has made necessary corrections. UA has uploaded coloured layout plan in additional douments and specific recommendation of DFO as per format will be submitted to your office via email.
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
13/10/2022
|
EDS
|
|
18
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
15/10/2022
|
Please upload the requisite documents
|
|
19
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
16/10/2022
|
The User Agency and DFO JV are requested to do the corrections as per EDS attached.
|
|
20
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (abhngh.761l@gov.in)
|
25/10/2022
|
The eds has been raised by PCCF/FCA/3393-5011-13 dated 15-10-2022
|
|