TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/Others/153363/2022              (ii). Name of Project for which Forest Land is required : Temporary permission of installation of Hot mix plant and crusher plant for Widening and Strengthening of the existing approach road from Digdole to Bajmasta in Connection with construction of new Adit at Urnihal to the tunnel T49A on Katra Banihal Section of USBRL Project.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Temporary permission of installation of Hot mix plant and crusher plant for Widening and Strengthening of the existing approach road from Digdole to Bajmasta in Connection with construction of new Adit at Urnihal to the tunnel T49A on Katra Banihal Section of USBRL Project.              (iv). File no. : 9-JKA-040/2022-Jammu              (v). State : Jammu and Kashmir              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.2421
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JK/Others/153363/202211/03/202215/03/2022   01/04/2022   04/04/2022   30/05/2022 Ramban Forest Division :31/05/2022Chenab Circle Doda:
  29/06/2022 (Ramban Forest Division)

Jammu and Kashmir:
30/06/2022
Jammu and Kashmir:
18/07/2022
Jammu:
02/08/2022
30/08/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Jammu and Kashmir) on:30/06/2022  
Replied by Circle(Chenab Circle Doda) on:05/07/2022  
Query raised by Circle (Chenab Circle Doda) on:01/07/2022  
Replied by DFO (Ramban Forest Division) on:05/07/2022  
Query raised by DFO (Ramban Forest Division) on:01/07/2022  
Replied by UA on :01/07/2022  
Query raised by DFO (Ramban Forest Division) on:02/07/2022  
Replied by UA on :03/07/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .