Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Samba forest Division)
|
EDS
|
User Agency (xenccdujh@gmail.com)
|
14/02/2020
|
Regarding MAP, KML files, Land for CA, FRA certificate
|
|
2
|
DFO (Billawar Forest Division)
|
EDS
|
User Agency (xenccdujh@gmail.com)
|
14/02/2020
|
1. FRL delineation
2. Mandatory Maps
3. Certificate regarding availbility of non-forest land for CA scheme
4. FRA certificates from Distt. Collector
|
|
3
|
DFO (Kathua Forest Division)
|
EDS
|
User Agency (xenccdujh@gmail.com)
|
19/02/2020
|
EDS regarding availability of non forest land for CA, certificate under FRA, 2006, Uploaded maps not in scale and are not legible, RoW width of proposed LMC & RMC and delineation of FRL, FRL-2 m & FRL - 4 m for submergence zone.
|
|
4
|
User Agency (xenccdujh@gmail.com)
|
REPLY
|
DFO (Kathua Forest Division)
|
18/03/2020
|
The correction have been made as per the instruction received
|
|
5
|
User Agency (xenccdujh@gmail.com)
|
REPLY
|
DFO (Samba forest Division)
|
18/03/2020
|
The correction have been made as per the instruction received
|
|
6
|
User Agency (xenccdujh@gmail.com)
|
REPLY
|
DFO (Billawar Forest Division)
|
18/03/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Billawar Forest Division)
|
EDS
|
User Agency (xenccdujh@gmail.com)
|
25/03/2020
|
1. FRL delineation 2. Mandatory Maps 3. Certificate regarding availbility of non-forest land for CA scheme 4. FRA certificates from Distt. Collector
|
|
8
|
User Agency (xenccdujh@gmail.com)
|
REPLY
|
DFO (Billawar Forest Division)
|
25/06/2020
|
The correction have been made as per the instruction received
|
|
9
|
Head Office
|
EDS
|
State secretary
|
10/08/2020
|
eds
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
11/08/2020
|
EDS by RO Chd may be provided
|
|
11
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
13/08/2020
|
kindly furnish/upload the requisite documents as desired by the Administrative Department/Regional Office Chandigarh
|
|
12
|
CF (East Circle Jammu)
|
EDS
|
DFO (Samba forest Division)
|
19/08/2020
|
kindly upload requisite documents
|
|
13
|
CF (East Circle Jammu)
|
EDS
|
DFO (Kathua Forest Division)
|
19/08/2020
|
kindly upload requisite documents
|
|
14
|
CF (East Circle Jammu)
|
EDS
|
DFO (Billawar Forest Division)
|
19/08/2020
|
kindly upload requisite documents
|
|
15
|
DFO (Billawar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
03/10/2020
|
Detailed CA Plan: Both for DFL and NFL uploaded on PARIVESH;
Additional Enumeration Lists at FRL-2m & FRL-4m also uploaded.
|
|
16
|
DFO (Kathua Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
05/10/2020
|
Corrective actions taken as per the EDS and incorporated in the CA Proposal which has been uploaded along with enumeration details at FRL-2 m & FRL-4 m as well. Further corrections in Part 1 needs to be done by the user agency as enlisted CF, East letter dated 30-09-2020.
|
|
17
|
DFO (Samba forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
05/10/2020
|
Reply to EDS in respect of Ujh Multipurpose Project
|
|
18
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
05/10/2020
|
necessary corrections made by dfo Billawar, Kathua and Samba but User agency could not make corrections as access to the portal was not available to them. UA has been asked to submit changes offline so that matter can be taken up with the Ministry
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
05/10/2020
|
Reply to EDS.
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
15/10/2020
|
User Agency may get EDS compliance uploaded through technical team
|
|
21
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
15/10/2020
|
Please ask the User Agency to upload the requisite documents in consultation with Technical Expert.
|
|
22
|
CF (East Circle Jammu)
|
EDS
|
DFO (Billawar Forest Division)
|
15/10/2020
|
pls ask UA to update necessary Docs
|
|
23
|
DFO (Billawar Forest Division)
|
EDS
|
User Agency (xenccdujh@gmail.com)
|
16/10/2020
|
EDS regarding uploading of data in respect of Ujh Multipurpose Project on PARIVESH.
|
|
24
|
User Agency (xenccdujh@gmail.com)
|
REPLY
|
DFO (Billawar Forest Division)
|
23/10/2020
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Billawar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
23/10/2020
|
The requisite details have been furnished by the User Agency. Therefore, the proposal may kindly be processed accordingly.
|
|
26
|
CF (East Circle Jammu)
|
EDS
|
DFO (Samba forest Division)
|
24/10/2020
|
CA Maps not seen. ipls upload
|
|
27
|
CF (East Circle Jammu)
|
EDS
|
DFO (Kathua Forest Division)
|
24/10/2020
|
CA Maps not seen. ipls upload
|
|
28
|
CF (East Circle Jammu)
|
EDS
|
DFO (Billawar Forest Division)
|
24/10/2020
|
CA Maps not seen. ipls upload
|
|
29
|
DFO (Billawar Forest Division)
|
EDS
|
User Agency (xenccdujh@gmail.com)
|
07/11/2020
|
Kindly furnish the revised Cost Benefit Analysis statement incorporating necessary change in view of the final approval of the CA plan of Ujh Multipurpose Project accorded by the office of PCCF, J&K. The copy of approval in enclosed herewith.
|
|
30
|
User Agency (xenccdujh@gmail.com)
|
REPLY
|
DFO (Billawar Forest Division)
|
08/11/2020
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Kathua Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
10/11/2020
|
Corrections as required have been incorporated.
|
|
32
|
DFO (Billawar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
10/11/2020
|
CA maps are already uploaded by the user agency
|
|
33
|
DFO (Samba forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
13/11/2020
|
Documents uploaded by the user agency
|
|
34
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
13/11/2020
|
UA submitted the required documents
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
13/11/2020
|
As desired, the needful has been done
|
|
36
|
State secretary
|
REPLY
|
Head Office
|
23/11/2020
|
Reply to EDS uploaded in EDS Letter.
|
|