TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/MIN/41321/2019              (ii). Name of Project for which Forest Land is required : Piparwar OCP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Piparwar ocp 43.30 ha was released vide letter no. F No. –F-8-172/1989-FC. Proposal for extension of diversion has been submitted on 5.2.2010. MoEF vide F No. –F-8-172/1989-FC(pt) dtd. 7.1.2010 issued letter about extension of period from 10 years to 30 years. This proposal includes 3 village.              (iv). State : Jharkhand              (v). Category of the Project : Mining              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 43.3
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/JH/MIN/41321/201927/01/202128/11/2022  22/09/2022  25/02/2021  24/09/2020  21/03/2020  03/08/2019   29/11/2022  11/11/2022  12/09/2022  27/01/2021  11/08/2020  13/02/2020  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at : Nodal Officer.