Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
29/07/2016
|
FRA NOC Of DC, COMPLETE RECLAMATION PLAN, Land - schedule of total land involved in the proposal ,print -out of online duly filled form etc...
|
|
2
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
30/09/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
30/09/2016
|
insufficient reply given to the queries raised by the division
|
|
4
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
01/10/2016
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
28/10/2016
|
during site inspection , it was found that the southeren side of the karma stone mining project, the pillars located falls in the jurisdiction of koderma forest division and also the pillars are very far located
|
|
6
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
31/10/2016
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
09/11/2016
|
submit revised proposal after correcting queries found on the field
|
|
8
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
14/11/2016
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
03/12/2016
|
shortcomings found in the site regarding proper allocation of pilllars
|
|
10
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
05/12/2016
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
13/12/2016
|
Regarding Change in the location of pillar no. BP1 falling outside village karma village boundry
|
|
12
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
17/12/2016
|
The correction have been made as per the instruction received
|
|
13
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
07/03/2017
|
Quaries raised by RCCF, Hazaribag in approval of proposal.
|
|
14
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
16/03/2017
|
Compliance report of queries done by C.F. T.circle, hazaribag is seeked from User agency.
|
|
15
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
19/03/2017
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
10/04/2017
|
Compliance of 04 queries raised.
|
|
17
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
15/04/2017
|
Unsatisfied compliance of queries submitted by DFO Hazaribagh West Division
|
|
18
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
08/05/2017
|
Compliance of query no.1 and 4 of the queries raised by RCCF Hazaribag.
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
10/08/2017
|
Clarification regarding difference in area mentioned in component wise break up and detail of lease area, correction in area of safety zone and whether the project is site specific has been sought.
|
|
20
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
11/08/2017
|
Please take note on query raised by GOJ
|
|
21
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
12/08/2017
|
Queries raised by Jharkhand State Government
|
|
22
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
16/08/2017
|
REVISED FORM-A needed with necessary corrections in Component wise break-up .
|
|
23
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
21/08/2017
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
29/08/2017
|
Compliancce of the queries is not as per the objections raised by govt. of Jharkhand.
|
|
25
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
05/09/2017
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
20/09/2017
|
compliance of queries raised by state govt.
|
|
27
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
20/09/2017
|
Justification for locating the project in forest area is not according to provisions of Forest Conservation Act 1980
|
|
28
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
26/09/2017
|
compliance report of queries forwarded.
|
|
29
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
04/10/2017
|
Unsatisfied compliance of queries submitted by DFO Hazaribagh West Division
|
|
30
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
06/10/2017
|
compete compiled compliance report of queries is sought.
|
|
31
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
06/10/2017
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
16/10/2017
|
revised compliance report is herby submitted.
|
|
33
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
18/10/2017
|
Compliance report of queries forwaded
|
|
34
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
28/12/2017
|
Please take note on query raised by Nodal.
|
|
35
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
09/01/2018
|
Please take note on query raised by Nodal Officer
|
|
36
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
09/01/2018
|
Reply of queries raised by PCCF-ED Ranchi vide letter no.- 1218 dt.- 28.12.2017 is sought
|
|
37
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
10/01/2018
|
The correction have been made as per the instruction received
|
|
38
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
24/01/2018
|
query compliance report is herby forwarded
|
|
39
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
07/02/2018
|
Compliance report is not satisfactory
|
|
40
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
13/02/2018
|
incomplete reply of the queries raised vide nodal officer letter no.1218 dated 28.12.2017
|
|
41
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
15/02/2018
|
The correction have been made as per the instruction received
|
|
42
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
07/03/2018
|
PCCF query has been replied
|
|
43
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
19/03/2018
|
Compliance report not submitted of query raised by Conservator of Forests
|
|
44
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (ramkoderma1010@gmail.com)
|
04/04/2018
|
incomplete proposal. queries raised for compliance.
|
|
45
|
User Agency (ramkoderma1010@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
06/04/2018
|
The correction have been made as per the instruction received
|
|
46
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
06/04/2018
|
Reply of queries raised by Conservator of Forest
|
|
47
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
07/04/2018
|
PCCF-cum-ED query has been replied
|
|
48
|
Nodal Officer
|
REPLY
|
State secretary
|
21/02/2019
|
EDS Reply
|
|
49
|
Regional Office
|
EDS
|
State secretary
|
01/11/2019
|
The proposal may be re-examined in the State Forest Department along with the full facts in context of the observation and recommendation of REC.
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
18/02/2020
|
Reply sought PCCF/Nodal Officer.
|
|
51
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
24/12/2020
|
Please take note on EDS by GOJ
|
|
52
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
04/01/2021
|
Please take note on EDS by GOJ
|
|
53
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
06/01/2021
|
The correction have been made as per the instruction received
|
|
54
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
08/01/2021
|
Reply of queries raised by GOJ
|
|
55
|
Nodal Officer
|
REPLY
|
State secretary
|
05/02/2021
|
EDS Reply
|
|
56
|
State secretary
|
REPLY
|
Regional Office
|
06/07/2021
|
Reply of query raised by RO Ranchi letter dated 24.07.2019 has been sent.
|
|
57
|
RO/HQ
|
EDS
|
( RORANCHI )
|
01/10/2021
|
EDS sought by Ministry on 13.09.2021
|
|