TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/155111/2022              (ii). Name of Project for which Forest Land is required : Work of Sohna Realignment of Rewari Sohna Palwal road NH 919 Old NH 71B from km 47.100to 49.350 in Sohna Hilly Portion on EPC mode in the State of Haryana.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : A greenfield road is to be constructed for Realignment of Rewari Sohna Palwal road NH 919 Old NH 71B from km 47.100to 49.350 in Sohna Hilly Portion. The project has been sanctioned by Ministry of Road Transport & Highways (MoRTH) Govt. of India.              (iv). State : Haryana              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 9.7884
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/ROAD/155111/202210/05/202223/05/2022   09/07/2022   10/08/2022   23/08/2022

Gurgaon :30/08/2022


Mewat :30/08/2022

C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Gurgaon) on:14/09/2022  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .