TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Pipeline/154707/2022              (ii). Name of Project for which Forest Land is required : Laying of Natural Gas Pipe Line from Barsat Chowk to Vardhaman Textile on Chora road Gharaunda to Kaimla road and Barsat to Barana road district Karnal              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Natural Gas Pipe Line from Barsat Chowk to Vardhaman Textile on Chaura road, Gharaunda to Kaimla road and Barsat to Barana road district Karnal Haryana.              (iv). State : Haryana              (v). Category of the Project : Pipeline              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.3375
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/Pipeline/154707/202228/04/202219/05/2022   22/05/2022   24/05/2022   13/06/2022 Karnal :16/06/2022Central Circle Rohtak:
  07/10/2022 (Karnal)

Haryana:
12/10/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Karnal) on:07/07/2022  
Replied by UA on :06/10/2022  
NOTE:- Proposal is pending at Nodal Officer .