TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/WATER/17373/2016              (ii). Name of Project for which Forest Land is required : Prov. LWSS Dorikhad to Batari, Kwanu, Jarol, Shilajan in GP Jarol in Tehsil Kumarsain District Shimla(H.P)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The fresh and adequate water is one of the basic need of community for prevention of water borne diseases and two improve the health status of public at large. This proposal is prepared to provide the drinking water for 18 No's villages of Gram Panchayat Jarol & Mailon. These villages are located on              (iv). File no. : Ft. 48-3256/2016 (FCA)              (v). State : Himachal Pradesh              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.1488
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HP/WATER/17373/201604/01/201620/01/2016  11/01/2016   28/04/2016  18/01/2016   07/05/2016   23/06/2016 Kotgarh :24/06/2016Rampur:
  05/07/2016 (Kotgarh)

Himachal Pradesh:
15/07/2016
Himachal Pradesh:
22/08/2016
16/08/2016
By :State Government
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)
Close(X)