TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/44200/2020              (ii). Name of Project for which Forest Land is required : C/o road from Kufar to Kanda Shilyar Gavan Sunna Bathal in G.P Halau KM 0/0 to 4/0              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : the road shall be increase the economy of the area with the sufficient cheap and quick transportation of possible agriculture produce easy and emergency medical help also be improve.              (iv). File no. : FC/HPB/06/33/2022              (v). State : Himachal Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.4037
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/44200/202025/01/202006/01/2021  18/12/2020  16/12/2020  07/12/2020  29/08/2020  10/02/2020   06/01/2021  01/01/2021  17/12/2020  12/12/2020  28/11/2020  28/08/2020   11/01/2021   03/02/2021 Chopal :03/02/2021Shimla:
  19/07/2021 (Chopal)

Himachal Pradesh:
16/08/2021
Himachal Pradesh:
23/10/2021
Shimla:
28/03/2022
15/09/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:10/05/2022  
Replied by State Government(Himachal Pradesh) on:12/08/2022  
Query raised by State Government (Himachal Pradesh) on:01/11/2021  
Replied by Nodal Officer (Himachal Pradesh) on:23/03/2022  
Query raised by State Government (Himachal Pradesh) on:11/05/2022  
Replied by Nodal Officer (Himachal Pradesh) on:12/08/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:15/09/2021  
Replied by Circle(Shimla) on:07/10/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:12/10/2021  
Replied by Circle(Shimla) on:18/10/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:01/11/2021  
Replied by Circle(Shimla) on:15/03/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:11/05/2022  
Replied by Circle(Shimla) on:06/08/2022  
Query raised by Circle (Shimla) on:26/07/2021  
Replied by DFO (Chopal) on:10/08/2021  
Query raised by Circle (Shimla) on:16/09/2021  
Replied by DFO (Chopal) on:01/10/2021  
Query raised by Circle (Shimla) on:06/10/2021  
Replied by DFO (Chopal) on:06/10/2021  
Query raised by Circle (Shimla) on:12/10/2021  
Replied by DFO (Chopal) on:13/10/2021  
Query raised by Circle (Shimla) on:11/11/2021  
Replied by DFO (Chopal) on:11/03/2022  
Query raised by Circle (Shimla) on:11/05/2022  
Replied by DFO (Chopal) on:17/05/2022  
Query raised by Circle (Shimla) on:18/05/2022  
Replied by DFO (Chopal) on:06/08/2022  
Query raised by DFO (Chopal) on:04/03/2021  
Replied by UA on :19/07/2021  
Query raised by DFO (Chopal) on:27/07/2021  
Replied by UA on :10/08/2021  
Query raised by DFO (Chopal) on:17/09/2021  
Replied by UA on :01/10/2021  
Query raised by DFO (Chopal) on:12/10/2021  
Replied by UA on :13/10/2021  
Query raised by DFO (Chopal) on:15/11/2021  
Replied by UA on :11/03/2022  
Query raised by DFO (Chopal) on:20/05/2022  
Replied by UA on :06/08/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .