TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/Others/51314/2020              (ii). Name of Project for which Forest Land is required : Construction of Sewerage Treatment Plant at Naddi, in Tehsil Dharamshala, District Kangra              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposal involves construction of Sewerage Treatment Plant at Naddi in Mohal Naddi, Tehsil Dharamshala, District Kangra H.P. The proposal requires 0.30 hectare of forest land for construction of Sewerage Treatment Plant and Dumping Site. Due to the increasing population of nearby areas and growi              (iv). File no. : FC/HPB/06/42/2021              (v). State : Himachal Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.3
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/Others/51314/202023/10/202001/02/2021  21/12/2020  27/10/2020   01/02/2021  19/01/2021  16/12/2020   10/02/2021   16/02/2021 D/sala :16/02/2021D/Sala:
  11/03/2021 (D/sala)

Himachal Pradesh:
03/06/2021
Himachal Pradesh:
06/10/2021
Shimla:
17/11/2021
06/07/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:13/12/2021  
Replied by State Government(Himachal Pradesh) on:29/06/2022  
Query raised by State Government (Himachal Pradesh) on:13/12/2021  
Replied by Nodal Officer (Himachal Pradesh) on:29/06/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:02/07/2021  
Replied by Circle(D/Sala) on:19/08/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:02/09/2021  
Replied by Circle(D/Sala) on:23/09/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:13/12/2021  
Replied by Circle(D/Sala) on:10/03/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:13/04/2022  
Replied by Circle(D/Sala) on:06/06/2022  
Query raised by Circle (D/Sala) on:16/03/2021  
Replied by DFO (D/sala) on:26/04/2021  
Query raised by Circle (D/Sala) on:27/04/2021  
Replied by DFO (D/sala) on:05/05/2021  
Query raised by Circle (D/Sala) on:06/07/2021  
Replied by DFO (D/sala) on:19/08/2021  
Query raised by Circle (D/Sala) on:04/09/2021  
Replied by DFO (D/sala) on:14/09/2021  
Query raised by Circle (D/Sala) on:21/12/2021  
Replied by DFO (D/sala) on:09/03/2022  
Query raised by Circle (D/Sala) on:16/04/2022  
Replied by DFO (D/sala) on:31/05/2022  
Query raised by DFO (D/sala) on:08/03/2021  
Replied by UA on :11/03/2021  
Query raised by DFO (D/sala) on:19/03/2021  
Replied by UA on :26/04/2021  
Query raised by DFO (D/sala) on:27/04/2021  
Replied by UA on :03/05/2021  
Query raised by DFO (D/sala) on:11/07/2021  
Replied by UA on :19/08/2021  
Query raised by DFO (D/sala) on:19/08/2021  
Replied by UA on :19/08/2021  
Query raised by DFO (D/sala) on:22/12/2021  
Replied by UA on :09/03/2022  
Query raised by DFO (D/sala) on:18/04/2022  
Replied by UA on :28/04/2022  
Query raised by DFO (D/sala) on:04/05/2022  
Replied by UA on :31/05/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .