Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
16/05/2019
|
original letter of RO adressed to DFO been attached in the Hard copy with the project name as JAL SAKTI project ,whearas the current proposal is named differently.
|
|
2
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
20/05/2019
|
Enumeration list of trees in original have been submitted to your office by user agency.
|
|
3
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
21/05/2019
|
Pls submit the corrected copy.
|
|
4
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
22/05/2019
|
Eds has been attended.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
29/05/2019
|
EDS
|
|
6
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
31/05/2019
|
Please attend to EDS
|
|
7
|
DFO (Mandi)
|
EDS
|
User Agency (hydelmicro100kw@gmail.com)
|
31/05/2019
|
Please attend EDS
|
|
8
|
User Agency (hydelmicro100kw@gmail.com)
|
REPLY
|
DFO (Mandi)
|
12/06/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Mandi)
|
EDS
|
User Agency (hydelmicro100kw@gmail.com)
|
14/06/2019
|
Please attend EDS
|
|
10
|
User Agency (hydelmicro100kw@gmail.com)
|
REPLY
|
DFO (Mandi)
|
15/06/2019
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
18/06/2019
|
EDS has been attended.
|
|
12
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
22/06/2019
|
EDS been attended to.
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
14/09/2020
|
EDS
|
|
14
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
14/09/2020
|
EDS
|
|
15
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
19/09/2020
|
EDS
|
|
16
|
DFO (Mandi)
|
EDS
|
User Agency (hydelmicro100kw@gmail.com)
|
19/09/2020
|
Pl attend EDS
|
|
17
|
User Agency (hydelmicro100kw@gmail.com)
|
REPLY
|
DFO (Mandi)
|
22/09/2020
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
22/09/2020
|
EDS has been attended.
|
|
19
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
24/09/2020
|
EDS have been attended.
|
|
20
|
Nodal Officer
|
EDS
|
CF (Mandi)
|
30/09/2020
|
The hard copy of part II with correct legal status of forest land has not been found attached with the reply.
|
|
21
|
CF (Mandi)
|
EDS
|
DFO (Mandi)
|
04/10/2020
|
The hard copy of part II with correct legal status of forest land has not been found attached with the reply.
|
|
22
|
DFO (Mandi)
|
REPLY
|
CF (Mandi)
|
07/10/2020
|
EDS has been attened.
|
|
23
|
CF (Mandi)
|
REPLY
|
Nodal Officer
|
12/10/2020
|
EDS has been attended.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
23/10/2020
|
Complete reply is submitted.
|
|