TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/ROAD/35147/2018              (ii). Name of Project for which Forest Land is required : Widening & Strenghtening Four lane of Navsari -Gandevi Road km 36/00 to 54/00              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Widening & Strenghtening Four lane of Navsari -Gandevi Road km 36/00 to 54/00              (iv). File no. : 6-GJB032/2019-BJP              (v). State : Gujarat              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 15.345
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/GJ/ROAD/35147/201803/08/201807/08/2018  07/08/2018   07/08/2018  07/08/2018   08/08/2018   24/08/2018 Navsari SF :24/08/2018Bharuch SF Circle:
  01/05/2019 (Navsari SF)

Gujarat:
09/05/2019
Gujarat:
27/05/2019
Gandhinagar:
26/06/2019
12/02/2020
By :Regional Office
Gujarat
04/06/2020
17/07/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:22/08/2019  
Replied by State Government(Gujarat) on:02/11/2019  
Query raised by Regional Office (Gandhinagar) on:08/01/2020  
Replied by State Government(Gujarat) on:07/02/2020  
Query raised by State Government (Gujarat) on:05/09/2019  
Replied by Nodal Officer (Gujarat) on:05/10/2019  
Query raised by State Government (Gujarat) on:17/01/2020  
Replied by Nodal Officer (Gujarat) on:30/01/2020  
Query raised by Nodal Officer (Gujarat) on:18/05/2019  
Replied by Circle(Bharuch SF Circle) on:20/05/2019  
Query raised by Nodal Officer (Gujarat) on:07/09/2019  
Replied by Circle(Bharuch SF Circle) on:26/09/2019  
Query raised by Nodal Officer (Gujarat) on:26/09/2019  
Replied by Circle(Bharuch SF Circle) on:30/09/2019  
Query raised by Nodal Officer (Gujarat) on:18/01/2020  
Replied by Circle(Bharuch SF Circle) on:25/01/2020  
Query raised by Nodal Officer (Gujarat) on:26/01/2020  
Replied by Circle(Bharuch SF Circle) on:28/01/2020  
Query raised by Circle (Bharuch SF Circle) on:20/05/2019  
Replied by DFO (Navsari SF) on:20/05/2019  
Query raised by Circle (Bharuch SF Circle) on:12/09/2019  
Replied by DFO (Navsari SF) on:25/09/2019  
Query raised by Circle (Bharuch SF Circle) on:27/09/2019  
Replied by DFO (Navsari SF) on:30/09/2019  
Query raised by Circle (Bharuch SF Circle) on:20/01/2020  
Replied by DFO (Navsari SF) on:24/01/2020  
Query raised by DFO (Navsari SF) on:01/05/2019  
Replied by UA on :01/05/2019  
Query raised by DFO (Navsari SF) on:25/09/2019  
Replied by UA on :25/09/2019  
Query raised by DFO (Navsari SF) on:27/09/2019  
Replied by UA on :27/09/2019  
NOTE:- Stage-II Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...