Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bhavnagar SF)
|
EDS
|
User Agency (exebvn@gmail.com)
|
19/06/2018
|
pls pay registration fee and processing fee
|
|
2
|
User Agency (exebvn@gmail.com)
|
REPLY
|
DFO (Bhavnagar SF)
|
05/07/2018
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Rajkot SF Circle)
|
12/09/2018
|
Plz upload FRA Certificate
|
|
4
|
CF (Rajkot SF Circle)
|
EDS
|
DFO (Bhavnagar SF)
|
12/09/2018
|
do as per instruction
|
|
5
|
DFO (Bhavnagar SF)
|
EDS
|
User Agency (exebvn@gmail.com)
|
12/09/2018
|
upload FRA certificate
|
|
6
|
User Agency (exebvn@gmail.com)
|
REPLY
|
DFO (Bhavnagar SF)
|
12/09/2018
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bhavnagar SF)
|
REPLY
|
CF (Rajkot SF Circle)
|
28/09/2018
|
query solved
|
|
8
|
CF (Rajkot SF Circle)
|
REPLY
|
Nodal Officer
|
28/09/2018
|
fra certificate uploded
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
29/11/2018
|
EDS on 29/11/2018
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
03/12/2018
|
goi query
|
|
11
|
Nodal Officer
|
EDS
|
CF (Rajkot SF Circle)
|
31/12/2018
|
as per goi letter
|
|
12
|
CF (Rajkot SF Circle)
|
EDS
|
DFO (Bhavnagar SF)
|
31/12/2018
|
do as per letter
|
|
13
|
DFO (Bhavnagar SF)
|
EDS
|
User Agency (exebvn@gmail.com)
|
01/01/2019
|
pls compliance as per latter
|
|
14
|
User Agency (exebvn@gmail.com)
|
REPLY
|
DFO (Bhavnagar SF)
|
02/01/2019
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Bhavnagar SF)
|
REPLY
|
CF (Rajkot SF Circle)
|
02/01/2019
|
solve
|
|
16
|
CF (Rajkot SF Circle)
|
REPLY
|
Nodal Officer
|
02/01/2019
|
done
|
|
17
|
Nodal Officer
|
EDS
|
CF (Rajkot SF Circle)
|
16/01/2019
|
as per goi letter
|
|
18
|
CF (Rajkot SF Circle)
|
EDS
|
DFO (Bhavnagar SF)
|
17/01/2019
|
as per goi leter
|
|
19
|
DFO (Bhavnagar SF)
|
EDS
|
User Agency (exebvn@gmail.com)
|
17/01/2019
|
uploud kml and solve query
|
|
20
|
User Agency (exebvn@gmail.com)
|
REPLY
|
DFO (Bhavnagar SF)
|
18/01/2019
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Bhavnagar SF)
|
REPLY
|
CF (Rajkot SF Circle)
|
08/02/2019
|
query solve
|
|
22
|
CF (Rajkot SF Circle)
|
REPLY
|
Nodal Officer
|
12/02/2019
|
correction done
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
12/02/2019
|
correction done
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
12/02/2019
|
reply done by nodal officer
|
|