TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/Pipeline/39543/2019   (ii). Name of Project for which Forest Land is required : Chhara LNG Pipeline Connectivity   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.060 Hect. Of Protected Forest Land (Road Side Strip land) for laying 36”dia Natural Gas Pipeline for transportation of Natural Gas from GSPL’s Lothpur CNG station in village Lothpur, Taluka Jafrabad, District Amreli to Chhara LNG Terminal Near Village Chhara, Taluka Kodinar in Distric   (iv). State : Gujarat   (v). Category of the Project : Pipeline   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 0.06
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/Pipeline/39543/201923/03/2019aa29/03/2019   17/04/2019 Amreli SF :20/04/2019Rajkot SF Circle:
  22/07/2019 (Amreli SF)

Gujarat:
02/08/2019
Gujarat:
16/09/2019
Bhopal:
08/01/2020
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Gujarat) on:04/10/2019  
Replied by Nodal Officer (Gujarat) on:06/01/2020  
Query raised by Nodal Officer (Gujarat) on:16/10/2019  
Replied by Circle(Rajkot SF Circle) on:06/01/2020  
Query raised by Circle (Rajkot SF Circle) on:11/11/2019  
Replied by DFO (Amreli SF) on:06/01/2020  
NOTE:- Proposal is pending at Regional Office .