TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/GJ/Others/30331/2017
(ii). Name of Project for which Forest Land is required :
National Optical Fiber Network(NOFN)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Under the National optical Fiber Network(NOFN) project of Government of India, RailTel Corporation of India Ltd. (RCIL) is implementing the phase I of the project in Gujarat state to connect 5315 Gram panchayats of 11 districts of Gujarat, by laying approx. 10071 Kms of optical fiber cable (OFC)
(iv). File no. :
C/JMN/T-6/280-83/2017-18
(v). State :
Gujarat
(vi). Category of the Project :
Others
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.263205
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Stage-I Approval on
Stage-II Approval on
FP/GJ/Others/30331/2017
18/11/2017
aa
27/11/2017
29/11/2017
Bharuch SF
:
01/12/2017
Bharuch SF Circle
:
24/01/2020 (
Bharuch SF
)
Gujarat
:
25/01/2020
Gujarat
:
26/01/2020
27/01/2020
By :State Government
13/05/2021
By :State Government
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by State Government (Gujarat) on:
28/04/2020
Replied by Nodal Officer (Gujarat) on:
13/05/2020
NOTE:-
Stage-II Approval accorded by :
State Government
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
State secretary
EDS
Nodal Officer
28/04/2020
R.O.Bhopal Return General Approval
2
Nodal Officer
REPLY
State secretary
13/05/2020
pl upload stage-1
EDS History(Stage-II)
×