TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GA/MIN/153183/2022              (ii). Name of Project for which Forest Land is required : Zamblidadga Dongor Iron and Manganese Ore Mine M.L. No. 3 FeMn 79              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project is proposed for the production of 0.5 MTPA of Iron Ore from the Mining Lease having an area of 70.20 Ha. and approach road (existing) to Mining Lease area admeasuring 1.88 Ha. is required for the project. Total forest land proposed for diversion for the project is 72.08 Ha., situated at              (iv). File no. : 8-26/2022-FC              (v). State : Goa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 72.08
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/GA/MIN/153183/202205/03/202205/04/2022  09/03/2022   24/05/2022  17/03/2022   15/06/2022   11/07/2022 South :12/07/2022Conservation:
  25/08/2022 (South)

Goa:
26/08/2022
Goa:
26/08/2022
06/09/2022
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 03/10/2022  
Query raised by State Government (Goa) on:10/10/2022  
Query raised by Nodal Officer (Goa) on:10/10/2022  
Query raised by Circle (Conservation) on:10/10/2022  
Replied by DFO (South) on:10/11/2022  
Query raised by DFO (South) on:23/08/2022  
Replied by UA on :24/08/2022  
Query raised by DFO (South) on:10/10/2022  
Replied by UA on :31/10/2022  
NOTE:- Proposal is pending at CF due to EDS raised by Head Office .