TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/DN/ROAD/35897/2018              (ii). Name of Project for which Forest Land is required : Diversion of roadside protected forest land for the Widening of road from Khanvel Chowk to Kherdi Border              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Widening of road from Khanvel Chowk to Kherdi Border (Ch. 19/6 to 26/6 Km)              (iv). State : Dadar & Nagar Haveli              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 7.7
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/DN/ROAD/35897/201814/09/2018aa20/09/2018   24/09/2018 Territorial Division :25/09/2018
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Territorial Division) on:10/12/2018  
Replied by UA on :18/06/2021  
Query raised by DFO (Territorial Division) on:08/08/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .