TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/DL/ROAD/142829/2021              (ii). Name of Project for which Forest Land is required : Construction of 6 Lane access controlled Highway from DND Maharani Bagh to Junction with Jaitpur-Pushta Road Section of NH-148 NA in the NCR of Delhi (PKG – I) under Bharatmala Pariyojana              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.35 Ha forest land for Construction of 6 Lane access controlled Highway from DND Maharani Bagh to Junction with Jaitpur-Pushta Road Section of NH-148 NA in the NCR of Delhi (PKG – I) under Bharatmala Pariyojana              (iv). File no. : 8B-RAJ041/2022-JPR              (v). State : Delhi              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.35
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/DL/ROAD/142829/202131/05/2021aa08/06/2021   28/07/2021 DCF South :29/07/2021Delhi:
  22/03/2022 (DCF South)

Delhi:
20/06/2022
Delhi:
27/06/2022
Lucknow:
27/06/2022
26/07/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Delhi) on:28/03/2022  
Replied by DFO (DCF South) on:01/06/2022  
Query raised by Circle (Delhi) on:15/06/2022  
Replied by DFO (DCF South) on:17/06/2022  
Query raised by DFO (DCF South) on:02/08/2021  
Replied by UA on :19/08/2021  
Query raised by DFO (DCF South) on:03/09/2021  
Replied by UA on :27/12/2021  
Query raised by DFO (DCF South) on:17/01/2022  
Replied by UA on :31/01/2022  
Query raised by DFO (DCF South) on:18/02/2022  
Replied by UA on :14/03/2022  
Query raised by DFO (DCF South) on:28/03/2022  
Replied by UA on :30/04/2022  
Query raised by DFO (DCF South) on:19/05/2022  
Replied by UA on :24/05/2022  
Query raised by DFO (DCF South) on:16/06/2022  
Replied by UA on :16/06/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...