TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/DL/RAIL/149368/2021              (ii). Name of Project for which Forest Land is required : Delhi-Gurugram-SNB RRTS Corridor              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The stabling line alignment for Delhi-Gurugram-SNB corridor will start from Sarai Kale Khan and terminate at Stabling Yard Complex at Jangpura, comprising terminal station, stabling yard, Operation Control Centre and other facilities for operations. Tree cutting permission is requested under FCA              (iv). File no. : 8B/DLI013/2022-JPR              (v). State : Delhi              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.282
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/DL/RAIL/149368/202116/11/202131/12/2021  24/11/2021  17/11/2021   31/12/2021  21/12/2021  18/11/2021   05/01/2022   05/01/2022 DCF South :13/01/2022Delhi:
  02/02/2022 (DCF South)

Delhi:
21/02/2022
Delhi:
22/02/2022
Jaipur:
24/02/2022
22/03/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Delhi) on:04/02/2022  
Replied by DFO (DCF South) on:11/02/2022  
Query raised by Circle (Delhi) on:14/02/2022  
Replied by DFO (DCF South) on:17/02/2022  
Query raised by Circle (Delhi) on:17/02/2022  
Replied by DFO (DCF South) on:17/02/2022  
Query raised by Circle (Delhi) on:18/02/2022  
Replied by DFO (DCF South) on:18/02/2022  
Query raised by DFO (DCF South) on:17/01/2022  
Replied by UA on :24/01/2022  
Query raised by DFO (DCF South) on:24/01/2022  
Replied by UA on :24/01/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .