TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/TRANS/43092/2019              (ii). Name of Project for which Forest Land is required : Modification of 220 KV Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of new BG Electrified East West Rail corridor from Gevra road-Pendra Road Railway Line Between location no. 278-281              (iv). State : Chhattisgarh              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 2.128
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/CG/TRANS/43092/201925/12/201925/01/2020   17/08/2020   26/08/2020   10/10/2020 Marwahi :12/10/2020
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Marwahi) on:14/02/2022  
Replied by UA on :17/10/2022  
NOTE:- Proposal is pending at DFO .
Close(X)
Close(X)
Please wait ...