TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/TRANS/33519/2018              (ii). Name of Project for which Forest Land is required : MAHAN SHP III HYROPOWER PROJECT              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : MAHAN SHP III HYROPOWER PROJECT              (iv). File no. : FC-II-CH-118-2019-NGP              (v). State : Chhattisgarh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 9.584
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/CG/TRANS/33519/201808/05/201809/05/2018   16/05/2018   24/05/2018   25/05/2018 Surajpur :31/05/2018Surguja:
  22/07/2019 (Surajpur)

Chhattisgarh:
27/07/2019
Chhattisgarh:
08/08/2019
Raipur:
18/09/2019
24/09/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Raipur) on:19/09/2019  
Replied by State Government(Chhattisgarh) on:23/09/2019  
Query raised by State Government (Chhattisgarh) on:20/09/2019  
Replied by Nodal Officer (Chhattisgarh) on:21/09/2019  
Query raised by DFO (Surajpur) on:22/06/2018  
Replied by UA on :01/07/2019  
NOTE:- Stage-I Approval accorded by : Regional Office .