TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/ROAD/151953/2022              (ii). Name of Project for which Forest Land is required : MEGHA - SINGPUR - DUGLI ROAD              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Upgradation Renewal and widening work of Megha - singpur - dugli Road. i/e culvert and bridge work. Total length 35 km. within is proposed 23.715 km. length. Forest land diversion.              (iv). State : Chhattisgarh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 37.973
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/CG/ROAD/151953/202209/02/202214/02/2022   29/04/2022   05/05/2022   05/05/2022 Dhamtari :05/05/2022Raipur:
  11/05/2023 (Dhamtari)

Chhattisgarh:
31/07/2023
Chhattisgarh:
17/08/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Raipur) on:29/02/2024  
Replied by State Government(Chhattisgarh) on:07/06/2024  
Query raised by Regional Office (Raipur) on:19/08/2024  
Query raised by State Government (Chhattisgarh) on:06/09/2023  
Replied by Nodal Officer (Chhattisgarh) on:15/09/2023  
Query raised by State Government (Chhattisgarh) on:27/03/2024  
Replied by Nodal Officer (Chhattisgarh) on:24/05/2024  
Query raised by State Government (Chhattisgarh) on:30/08/2024  
Query raised by Nodal Officer (Chhattisgarh) on:07/08/2023  
Replied by Circle(Raipur) on:10/08/2023  
Query raised by Nodal Officer (Chhattisgarh) on:01/04/2024  
Replied by Circle(Raipur) on:22/05/2024  
Query raised by Nodal Officer (Chhattisgarh) on:07/10/2024  
Replied by Circle() on:  
Query raised by Circle (Raipur) on:23/06/2023  
Replied by DFO (Dhamtari) on:24/07/2023  
Query raised by Circle (Raipur) on:07/08/2023  
Replied by DFO (Dhamtari) on:08/08/2023  
Query raised by Circle (Raipur) on:08/04/2024  
Replied by DFO (Dhamtari) on:24/04/2024  
Query raised by Circle (Raipur) on:11/11/2024  
Replied by DFO () on:  
Query raised by DFO (Dhamtari) on:17/05/2022  
Replied by UA on :18/04/2023  
Query raised by DFO (Dhamtari) on:05/07/2023  
Replied by UA on :19/07/2023  
Query raised by DFO (Dhamtari) on:08/04/2024  
Replied by UA on :09/04/2024  
Query raised by DFO (Dhamtari) on:21/11/2024  
Replied by UA on :  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .
Close(X)
Close(X)