TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/Others/21077/2016              (ii). Name of Project for which Forest Land is required : Aadivashi Shramikon ke vishram keliye Shed Sthapit karne hetu              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Establishment of Rest House, Toilets,Store Rooms, Weigh Bridge, Kitchen Rooms, First AID Rooms etc for Approximately 450-500 Labours.              (iv). State : Chhattisgarh              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.163
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/CG/Others/21077/201623/08/201624/09/2019  31/05/2018  16/02/2018  17/09/2016   24/03/2021  03/09/2019  08/03/2018  10/02/2018   31/03/2021   05/04/2021 Bastar :06/04/2021
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Bastar) on:07/08/2021  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .