TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/MIN/39553/2019              (ii). Name of Project for which Forest Land is required : BHATGAON UG MINE              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for diversion of 230.78 Ha. of Forest land ( 63.93 Ha. Reserve Forest & 166.85 Ha. Revenue forest land) for Coal mining in Bhatgaon UG Mine of SECL, Bhatgaon Area in surajpur District of Chhattisgarh.              (iv). State : Chhattisgarh              (v). Category of the Project : Mining              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 230.78
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR)Stage-I Approval onStage-II Approval on
FP/CG/MIN/39553/201918/06/201914/10/2019  16/08/2019   14/10/2019  27/09/2019   31/10/2019   04/11/2019 Surajpur :11/11/2019
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by DFO (Surajpur) on:27/11/2019  
Replied by UA on :29/05/2020  
Query raised by DFO (Surajpur) on:27/07/2020  
Replied by UA on :09/06/2022  
Query raised by DFO (Surajpur) on:26/08/2022  
Replied by UA on :18/10/2022  
NOTE:- Proposal is pending at DFO .