TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/HYD/36355/2018              (ii). Name of Project for which Forest Land is required : GAMMARMUND Small Hydro Power Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Power Generation              (iv). State : Chhattisgarh              (v). Category of the Project : Hydel              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 8.136
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onStage-II Approval on
FP/CG/HYD/36355/201805/10/201814/12/2018  01/11/2018  08/10/2018   11/06/2019  16/11/2018  25/10/2018   18/09/2019   17/10/2019 Bastar :18/10/2019
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Bastar) on:22/06/2020  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .